Answering: “Creating a forecast for a Sprint tends to run more smoothly when the Product Backlog items that are discussed are well understood and actionable. Which approach would you recommend to ensure this state of Product Backlog at Sprint Planning?”
Creating a forecast for a Sprint tends to run more smoothly when the Product Backlog items that are discussed are well understood and actionable. Which approach would you recommend to ensure this state of Product Backlog at Sprint Planning?
(choose the best answer)
A. A separate Scrum Team of business analysts and functional testers analyze high-ordered requirements one Sprint ahead of development.
B. The Product Owner work with the stakeholders to prepare Product Backlog items outside of the Sprint so the Developers will not be disrupted.
C. The analysts on the Scrum Team document high-ordered Product Backlog items during a Sprint when they are not busy working on the forecast.
D. The Scrum Team uses some time in each Sprint to analyze, estimate and design high-ordered Product Backlog items.