Assisting the Product Owner with Delays in a Complex Project
In a complex project involving multiple components and systems, delays can occur due to various reasons such as changes in interfaces and unavailability of testing infrastructure. As a Scrum Master, it is crucial to effectively manage such situations and support the Product Owner in addressing stakeholder concerns. This article explores a specific exam question about how a Scrum Master can help the Product Owner in a scenario where the team needs additional Sprints to deliver the functionality, providing detailed explanations and insights relevant to the PSM II exam.
Exam Question
Eight months ago your company started development of a new platform consisting of several components and systems. You are the Scrum Master on the team building the “core” application of the platform; your application connects all other systems. The Scrum Teams work in monthly Sprints, and the team is expected to deliver all functionality in three Sprints. Recently the team’s progress was slowed down because of changes to interfaces of other components that you integrate with, as well as unavailability of the program’s testing infrastructure. The program manager is extremely upset and angry when they find out that the team will need two more Sprints. The project managers of the other components confirm their adherence to the expected date. As a Scrum Master, what could you do to help the Product Owner? (choose the best answer)
- A. You suggest working with the program manager and the project managers of the other systems on the ordering and the value of your open Product Backlog items to redefine the possible delivery date.
- B. You shorten your Sprints to be ready sooner.
- C. You inform the program manager that there is a way. You remove all items from the Product Backlog for which development is forecasted to be beyond the expected date. These are likely to be low value anyhow.
- D. You calculate how many additional developers it would take to increase velocity in order to make the original date. You inform the program manager of the additional budget for these developers. This would then allow making the expected date.
Correct Answer
A. You suggest working with the program manager and the project managers of the other systems on the ordering and the value of your open Product Backlog items to redefine the possible delivery date.
Explanation
Correct Answer
A. You suggest working with the program manager and the project managers of the other systems on the ordering and the value of your open Product Backlog items to redefine the possible delivery date: This approach involves collaborating with key stakeholders to re-evaluate the priorities and values of the remaining Product Backlog items. By redefining the possible delivery date based on the most valuable items, you ensure that the team focuses on delivering the highest value within the given constraints. This strategy promotes transparency, stakeholder involvement, and realistic planning.
Incorrect Answers
B. You shorten your Sprints to be ready sooner: Shortening Sprints does not necessarily increase productivity or address the root causes of the delays. It may lead to rushed work and compromised quality, which contradicts Scrum principles of delivering potentially shippable increments.
C. You inform the program manager that there is a way. You remove all items from the Product Backlog for which development is forecasted to be beyond the expected date. These are likely to be low value anyhow: Arbitrarily removing items from the Product Backlog without a thorough evaluation of their value can lead to significant gaps in functionality and does not address the underlying issues. It also undermines the Product Owner’s role in managing the Product Backlog.
D. You calculate how many additional developers it would take to increase velocity in order to make the original date. You inform the program manager of the additional budget for these developers. This would then allow making the expected date: Adding more developers to a project late in the development cycle often leads to diminishing returns due to the complexities of team dynamics and the learning curve. It can also increase overhead and disrupt the existing team’s workflow.
Responsibilities in Scrum
- Product Owner: The Product Owner is responsible for managing the Product Backlog, ensuring that it is well-ordered and reflects the highest value items. They decide on the prioritization of incomplete items returned to the Product Backlog.
- Scrum Master: The Scrum Master facilitates collaboration and communication among the Scrum Team and stakeholders. They help remove impediments, ensure adherence to Scrum practices, and support the team in delivering valuable increments.
- Developers: Developers are responsible for delivering potentially shippable increments at the end of each Sprint. They collaborate with the Product Owner and Scrum Master to ensure that work is prioritized and completed effectively.
Relevance to the PSM II Exam
Understanding how to manage delays and stakeholder expectations is crucial for the PSM II exam. It demonstrates advanced knowledge of Scrum principles and the role of the Scrum Master in facilitating effective collaboration and realistic planning. Mastering this concept ensures that Scrum Masters can guide their teams in maintaining high-quality standards and delivering value within constraints.
Key Takeaways
- Collaborating with stakeholders to re-evaluate priorities and redefine delivery dates promotes transparency and realistic planning.
- Shortening Sprints or arbitrarily removing backlog items can compromise quality and value.
- Adding more developers late in the development cycle often leads to diminishing returns and increased overhead.
Conclusion
Managing delays in a complex project requires effective collaboration, realistic planning, and prioritization of high-value items. By working with stakeholders to re-evaluate the Product Backlog and redefine delivery dates, the Scrum Master supports the Product Owner in addressing concerns and ensuring that the team delivers valuable increments within constraints. Understanding these principles is crucial for effective Scrum implementation and success in the PSM II exam.

Get ready for the official PSM II exam
90 PSM II practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 30 random questions in 90 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM II exam fee ($250) is paid separately to Scrum.org.
More PSM II exam questions
- You are the Scrum Master for four teams working from the same Product Backlog. Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full time commitment from Stella, an external specialist who is not a member of any of the four Scrum Teams. What would you consider acceptable solutions for the problem?
- At the ninth Sprint Retrospective, the Product Owner is very disappointed and angry. She has determined that the technical debt has increased, and the product is not meeting her expectations. The product will need a few more Sprints to meet the scalability requirements. Which of the following could be true? Select the best response.
- Which two of these situations best demonstrate that the Developers are self-managing?
- A Scrum Team consists of Developers working from globally distributed locations. Organizing the Scrum events requires conferencing tools that are not easily available within the organization. The Developers propose doing a Daily Scrum only on Tuesdays. Which are the most appropriate responses for their Scrum Master?
- You are the Scrum Master of a Scrum Team that is new to Scrum. The Product Owner comes to you halfway through the Sprint and says, “I don’t feel like the Developers will be able to meet their commitment to deliver the Product Backlog items selected during Sprint Planning.” What should you do in this situation?