Commitments of the Scrum Team Each Sprint
In each Sprint, the Scrum Team commits to several key actions to ensure successful delivery and adherence to Scrum principles. This article addresses a specific exam question about what the Scrum Team commits to during each Sprint.
Exam Question
What does the Scrum Team commit to each Sprint? (choose the best three answers)
- A. Increasing velocity.
- B. Seeking stakeholder feedback.
- C. Working towards the Sprint Goal.
- D. Upholding transparency.
- E. Having the Product Owner available to the Developers on a daily basis.
- F. Getting all the forecasted work in the Sprint Plan done.
Correct Answers
B. Seeking stakeholder feedback.
C. Working towards the Sprint Goal.
D. Upholding transparency.
Explanation
Correct Answers
B. Seeking stakeholder feedback:
Seeking feedback from stakeholders is a crucial part of the Scrum process. During the Sprint Review, the Scrum Team presents the Increment to stakeholders to gather their feedback. This helps ensure that the product is meeting their needs and allows for any necessary adjustments.
C. Working towards the Sprint Goal:
The Sprint Goal provides direction and focus for the Sprint. The Scrum Team commits to working towards achieving the Sprint Goal, which is a collaborative effort defined during Sprint Planning. This goal helps guide the team’s efforts and ensures that they are aligned on what needs to be accomplished.
D. Upholding transparency:
Transparency is one of the pillars of Scrum and is crucial for inspection and adaptation. The Scrum Team commits to being open and transparent about their progress, challenges, and any issues they face. This includes maintaining clear and visible artifacts, such as the Product Backlog and Sprint Backlog, and ensuring that all stakeholders have a clear understanding of the work being done.
Incorrect Answers
A. Increasing velocity:
While increasing velocity can be a goal, it is not something the Scrum Team commits to each Sprint. Velocity is a measure of the amount of work a team completes in a Sprint and can vary due to numerous factors. The focus should be on delivering value and quality rather than solely increasing velocity.
E. Having the Product Owner available to the Developers on a daily basis:
The availability of the Product Owner is essential for clarifications and decision-making, but it is not a specific commitment made by the Scrum Team each Sprint. The focus is more on the collaborative effort to achieve the Sprint Goal and maintain transparency.
F. Getting all the forecasted work in the Sprint Plan done:
The Scrum Team commits to the Sprint Goal, which is realized through the forecasted work. The Sprint Backlog is a living artifact that evolves throughout the Sprint. A forecast is based on the information available at the time and can change as new information emerges. The commitment is to strive to achieve the Sprint Goal, even if the specific work items in the forecast may need to adapt.
Responsibilities in Scrum
- Product Owner: Ensures that the Product Backlog is well-refined and that the most valuable items are prioritized. Collaborates with the Scrum Team to set a clear Sprint Goal.
- Scrum Master: Facilitates the Scrum process, helps remove impediments, and ensures that the Scrum Team adheres to Scrum principles, including transparency.
- Developers: Commit to delivering the forecasted work and achieving the Sprint Goal. They work collaboratively to maintain transparency and address any challenges that arise.
Relevance to the PSM II Exam
Understanding the key commitments of the Scrum Team during each Sprint is crucial for the PSM II exam. This knowledge demonstrates an advanced understanding of Scrum practices and the ability to effectively guide and support Scrum Teams in achieving their objectives.
Key Takeaways
- The Scrum Team commits to seeking stakeholder feedback, working towards the Sprint Goal, and upholding transparency.
- Increasing velocity and having the Product Owner available daily are important but are not specific commitments made each Sprint.
- The focus should be on delivering value, maintaining transparency, and achieving the Sprint Goal.
Conclusion
Each Sprint, the Scrum Team commits to seeking stakeholder feedback, working towards the Sprint Goal, and maintaining transparency. These commitments are essential for ensuring successful delivery and adherence to Scrum principles.

Get ready for the official PSM II exam
90 PSM II practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 30 random questions in 90 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM II exam fee ($250) is paid separately to Scrum.org.
More PSM II exam questions
- Respect is one of the five Scrum values. Which statements demonstrate respectful behavior in the Scrum Team?
- The Developer’s Daily Scrum is scheduled to start at 10:00 each day. Team members turn up late, and once everyone is assembled, the Daily Scrum starts. By then it is typically 4 to 5 minutes for people to transport within the building.
- The Developers are waiting for an external supplier to deliver a specific product component that they need to integrate and use. Without that component there will not be enough work in the next Sprint to occupy the full team. They ask their Product Owner to re-order the Product Backlog. The Product Owner asks the Scrum Master for help. What would be good advice for the Product Owner?
- User documentation is part of the Definition of Done. However, there are not enough technical writers to go around. Your Scrum Team does not have a Technical Writer. What needs to be done?
- The Scrum Master is a true leader. How does a Scrum Master demonstrate true leadership?