Select two ways that time-boxing promotes self-organization

Answering: “Select two ways that time-boxing promotes self-organization.”

An important pillar of Scrum is the management principle of self-organization. Select two ways that time-boxing promotes self-organization.
(choose the best two answers)
A. Time-boxes encourage the people who are closest to the problem to create the best possible result in the time allotted, give the current context.
B. Time-boxes help everyone focus on the same problem at the same time.
C. Time-boxes eliminate politics and bureaucracy.
D. Time-boxing protects the Development Team from the Product Owner so developers can actually focus.
E. Teams can determine on their own how much overtime is acceptable for a time-box, generally expressed as a percentage of the time-box.
F. Time-boxes do not allow enough time for stringent processes or meeting overhead.

Answering: “Select two ways that time-boxing promotes self-organization.” Read More »

What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint

Answering: “What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?” (PSM I)

What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?
(choose the best answer)
A. Refine the Product Backlog.
B. Update the project plan with stakeholders.
C. There are no such activities. The next Sprint starts immediately after the current Sprint.
D. Work with the Quality Assurance departments on the Increment of the current Sprint.

Answering: “What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?” (PSM I) Read More »

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog

Answering: “How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?” (PSM I)

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
(choose the best answer)
A. The Developers pull in work in agreement with the Product Owner.
B. The Product Owner should provide each team with its own Product Backlog.
C. Each Scrum Team takes an equal number of items.
D. The Product Owner decides.
E. The Scrum Team with the highest velocity pulls Product Backlog items first.

Answering: “How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?” (PSM I) Read More »