Timing of the Second Sprint in Scrum
In Scrum, the start and end of Sprints follow a consistent and predictable pattern, ensuring a continuous flow of work and feedback. Let’s explore when the second Sprint begins within the Scrum framework.
Exam Question
When does the second Sprint start? (choose the best answer)
- A. Immediately after the first Sprint.
- B. After the Product Backlog items for the second Sprint has been selected.
- C. Once the architectural changes for the second Sprint are approved by the senior architect.
- D. After the customer completes acceptance testing of the first Sprint.
Correct Answer
A. Immediately after the first Sprint.
Explanation
Why A is Correct
A. Immediately after the first Sprint:
In Scrum, Sprints are continuous and follow one another without any breaks in between. As soon as one Sprint ends, the next Sprint begins immediately. This ensures that the team maintains a consistent cadence and maximizes the delivery of value.
Why B, C, and D are Incorrect
B. After the Product Backlog items for the second Sprint has been selected:
The selection of Product Backlog items for the next Sprint happens during the Sprint Planning meeting, which is part of the process that kicks off the new Sprint.
C. Once the architectural changes for the second Sprint are approved by the senior architect:
Scrum does not require approval from a senior architect to begin a Sprint. Decisions about architecture are made by the Scrum Team as part of their collaborative work.
D. After the customer completes acceptance testing of the first Sprint:
Acceptance testing is part of the definition of “Done” for the increment delivered in the Sprint. The new Sprint starts immediately after the previous one ends, independent of external acceptance testing.
Key Points
- Continuous Flow: Sprints follow one another without gaps, ensuring a continuous flow of work.
- Sprint Planning: The planning for the next Sprint happens at the beginning of the new Sprint, ensuring that the team is always prepared to move forward.
- Team Autonomy: The Scrum Team collectively makes decisions about architecture and other aspects of the work during the Sprint.
Responsibilities in Scrum
- Product Owner: Ensures the Product Backlog is ordered and refined to maximize the value delivered each Sprint.
- Scrum Master: Facilitates the Sprint Review and Sprint Planning meetings, ensuring a smooth transition from one Sprint to the next.
- Developers: Collaboratively plan and execute the work for the new Sprint, immediately following the conclusion of the previous Sprint.
Relevance to the PSM I Exam
Understanding the timing and flow of Sprints is crucial for the PSM I exam. This knowledge helps candidates appreciate the continuous nature of Scrum and the importance of maintaining a steady cadence of work and feedback.
Conclusion
In Scrum, the second Sprint starts immediately after the first Sprint concludes. This continuous flow ensures that the team maintains a consistent cadence and maximizes the delivery of value. Understanding this principle is essential for effective Scrum implementation.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- What is the responsibility of the Product Owner in crafting the Sprint Goal?” (PSM I)
- Which output from Sprint Planning provides the Scrum Team with a target and overarching direction for the Sprint?” (PSM I)
- True or False: The Product Owner makes sure the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders.” (PSM I)
- What is the timebox for the Sprint Planning event?” (PSM I)
- As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?” (PSM I)