PSM I exam question
What is the timebox for the Sprint Planning event

Answering: “What is the timebox for the Sprint Planning event?” (PSM I)

By Hiro TakashimyaUpdated
Studying for the PSM I exam? Try 20 free practice questions first.Start the free quiz →

Timebox for the Sprint Planning Event in Scrum

Sprint Planning is a crucial event in Scrum where the Scrum Team comes together to plan the work for the upcoming Sprint. Let’s examine the timebox for the Sprint Planning event.

Exam Question

What is the timebox for the Sprint Planning event? (choose the best answer)

  • A. 4 hours for a one-month Sprint.
  • B. 8 hours for a one-month Sprint.
  • C. Whenever it is done.
  • D. Monthly.

Correct Answer

B. 8 hours for a one-month Sprint.

Explanation

Why B is Correct

B. 8 hours for a one-month Sprint:

According to the Scrum Guide, the timebox for the Sprint Planning event is a maximum of 8 hours for a one-month Sprint. For shorter Sprints, this event is usually shorter. This timebox ensures that the team has adequate time to discuss and plan the work for the upcoming Sprint while maintaining a focus on efficiency and productivity.

Why A, C, and D are Incorrect

A. 4 hours for a one-month Sprint:

This duration is incorrect. The correct timebox is 8 hours for a one-month Sprint.

C. Whenever it is done:

While Scrum emphasizes completing events within their timebox, the “whenever it is done” approach contradicts the principle of having a fixed maximum duration for each event.

D. Monthly:

This answer is incorrect as it does not specify the duration of the Sprint Planning event but rather suggests a frequency, which is not aligned with the concept of timeboxing.

Key Points

  • Fixed Timebox: The Sprint Planning event is timeboxed to a maximum of 8 hours for a one-month Sprint, ensuring a structured and efficient planning process.
  • Scalability: The timebox is proportionally shorter for shorter Sprints, maintaining the same efficiency.

Responsibilities in Scrum

  • Product Owner: Ensures the Product Backlog is ordered and refined to provide a clear and prioritized list of items for the upcoming Sprint.
  • Scrum Master: Facilitates the Sprint Planning event, ensuring it stays within the timebox and that all necessary discussions and planning occur.
  • Developers: Collaborate to define the work they will undertake during the Sprint, creating a Sprint Backlog and setting a Sprint Goal.

Relevance to the PSM I Exam

Understanding the timeboxes for various Scrum events, including Sprint Planning, is crucial for the PSM I exam. This knowledge helps candidates appreciate the structured approach of Scrum and the importance of maintaining timeboxes for efficiency and effectiveness.

Conclusion

In Scrum, the Sprint Planning event is timeboxed to a maximum of 8 hours for a one-month Sprint. This fixed duration ensures a structured and efficient planning process, enabling the Scrum Team to effectively plan and prepare for the upcoming Sprint.

Scrum Master PSM I™ Exam Prep

Get ready for the official PSM I exam

480 PSM I practice questions, each with an in-depth explanation like the one above.

  • Practice Mode: study at your own pace and choose the test length.
  • Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.

$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.

More PSM I exam questions

Practice all 480 PSM I questions →

You cannot copy content of this page