By the end of Sprint Planning, enough of the Sprint Backlog must be defined for the Developers to forecast what they can do. The rest emerges as the Sprint goes on.
Exam Question
How much of the Sprint Backlog must be defined during the Sprint Planning event? (choose the best answer)
- A. Enough so the Developers can create their forecast of what they can do.
- B. Just enough tasks for the Scrum Master to be confident in the Developers’ understanding of the Sprint.
- C. Just enough to understand design and architectural implications.
- D. The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning event.
Correct Answer
A. Enough so the Developers can create their forecast of what they can do.
Why This Is the Correct Answer
Sprint Planning answers why the Sprint is valuable, what can be done and how it will get done. The Developers select items, craft the plan and form a forecast of what they believe they can deliver toward the Sprint Goal. The Scrum Guide notes that the Developers often plan by decomposing items into work of one day or less, but it leaves the method up to them. Full detail up front is neither possible nor useful in complex work. The Guide says “The Sprint Backlog is updated throughout the Sprint as more is learned,” so planning only needs to go deep enough to start with confidence.
Why the Other Options Are Wrong
B. Enough tasks for the Scrum Master to be confident in the Developers’ understanding. The plan is by and for the Developers. The Scrum Master is not the one who needs to be satisfied.
C. Just enough to understand design and architectural implications. Design is part of the conversation, but the purpose of planning is a forecast and a plan toward the Sprint Goal.
D. The entire Sprint Backlog must be identified and estimated. This is upfront planning. In complex work, details emerge during the Sprint and the plan adapts.
Exam Tip
For “how much must be done in Sprint Planning” questions, avoid answers that demand everything up front or that satisfy someone other than the Developers.
Key Takeaways
- Sprint Planning creates enough of a plan to start.
- The Sprint Backlog emerges throughout the Sprint.
- The plan serves the Developers, not observers.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- True or False: The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.” (PSM I)
- Answering “True or False: The Sprint Goal is selected before the Sprint Backlog is created
- Which of the following are appropriate topics for discussion during a Sprint Retrospective?” (PSM I)
- Developers are self-managing, which of the following do they manage?” (PSM I)
- When the Developers determine that they will not be able to finish the complete forecast, who should be present when reviewing and adjusting the Sprint work selected

