Answering: “When the Developers determine that they will not be able to finish the complete forecast, who should be present when reviewing and adjusting the Sprint work selected”
When the Developers determine that they will not be able to finish the complete forecast, who should be present when reviewing and adjusting the Sprint work selected?
(choose the best answer)
A. The Product Owner and all stakeholders.
B. The Product Owner and the Developers.
C. The Scrum Master and the Developers.
D. The Scrum Master, the project manager and the Developers.