Answering “Who can cancel a Sprint?”
Who can cancel a Sprint?
(choose the best answer)
A. The Stakeholders.
B. The Scrum Master.
C. The Scrum Team.
D. The Product Owner.
Answering “Who can cancel a Sprint?” Read More »
Who can cancel a Sprint?
(choose the best answer)
A. The Stakeholders.
B. The Scrum Master.
C. The Scrum Team.
D. The Product Owner.
Answering “Who can cancel a Sprint?” Read More »
True or False: Developers do not meet with stakeholders; only the Product Owner meets with stakeholders.
A. True
B. False
Which answer best describes the topics covered in Sprint Planning?
(choose the best answer)
A. Who is on the team and what team member roles will be.
B. What to do and who will do it.
C. How conditions have changed and how the Product Backlog should evolve.
D. What went wrong in the last Sprint and what to do differently this Sprint.
E. What can be done, how to do it, and why to do it.
Answering: “Which answer best describes the topics covered in Sprint Planning?” (PSM I) Read More »
How do you know that a Scrum Team is cross-functional?
(choose the best answer)
A. Every member of the Scrum Team is able to perform every task.
B. The Scrum Team has all the skills to create an Increment by the end of every Sprint.
C. There are no conflicts within the Scrum Team.
D. A few of the Developers pair program and do Test-Driven Development.
Answering: “How do you know that a Scrum Team is cross-functional?” Read More »
True or False: Cross-functional teams are optimized to work on one component or layer of a system only.
A. True
B. False
At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built both will not meet their needs and will cost more than they are willing to spend. What factors may have led to this?
(choose the best two answers)
A. The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.
B. The Product Owner has not been keeping the stakeholders aware of the progress of the project.
C. The Project Management Office (PMO) has not been engaged adequately.
D. The stakeholders were not allowed to prioritize the Product Backlog items.
Answering: “At the seventh Sprint Review, the stakeholders are disappointed” Read More »