Answering: “A Scrum Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what done means.”

A Scrum Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what done means.
(choose the best two answers)
A. Ready to be released to end users.
B. All work the Developers are willing to do.
C. Whatever the Product Owner defines as quality.
D. Ready for integration.
E. No work left from the Definition of Done.

Answering: “A Scrum Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what done means.” Read More »

Answering: “For the purpose of transparency, when does Scrum say a valuable and useful Increment must be available?”

For the purpose of transparency, when does Scrum say a valuable and useful Increment must be available?
(choose the best answer)
A. Before the Release Sprint.
B. After the Acceptance Testing phase.
C. At the end of every Sprint.
D. Every 3 Sprints.
E. When the Product Owner asks to create one.

Answering: “For the purpose of transparency, when does Scrum say a valuable and useful Increment must be available?” Read More »