Ownership of the Sprint Backlog
In Scrum, understanding the ownership and responsibilities related to the Sprint Backlog is crucial. This knowledge helps ensure that the team operates efficiently and effectively. This topic is often tested in the PSM I exam.
Exam Question
Who owns the Sprint Backlog?
(choose the best answer)
- A. The Scrum Team.
- B. The Developers.
- C. The Product Owner.
- D. The Scrum Master.
Correct Answer
B. The Developers.
Explanation
Why B is Correct
B. The Developers: The Sprint Backlog is a subset of the Product Backlog, containing tasks that the Developers have identified as necessary to meet the Sprint Goal. The Developers own the Sprint Backlog because they are responsible for planning, managing, and executing the work during the Sprint. Ownership by the Developers ensures that they have full control over how they organize and complete the work, promoting accountability and self-management.
Key Points
- Developer Ownership: The Developers are solely responsible for the Sprint Backlog, including its creation, modification, and execution during the Sprint.
- Accountability: This ownership aligns with the principle of self-management, where the Developers manage their own work and commitments.
- Adaptability: The Developers can adjust the Sprint Backlog as needed during the Sprint to ensure they meet the Sprint Goal.
Responsibilities in Scrum
- Product Owner: Ensures the Product Backlog is ordered and refined to maximize value and align with the team’s capacity. The Product Owner is accountable for effective Product Backlog management.
- Scrum Master: Facilitates communication and ensures the Scrum framework is followed, supporting the Product Owner and Developers in their roles.
- Developers: Own the Sprint Backlog, collaborate to complete all tasks necessary to deliver a potentially shippable Increment, and ensure all work aligns with the Sprint Goal.
Relevance to the PSM I Exam
Understanding who owns the Sprint Backlog and the responsibilities of the Developers in managing it is crucial for the PSM I exam. This knowledge underscores the importance of self-management and accountability within the Scrum framework.
Conclusion
In summary, the Developers own the Sprint Backlog, reflecting their responsibility for planning, managing, and executing the work during the Sprint. This ownership promotes accountability and ensures that the team remains focused on meeting the Sprint Goal.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
- The Developers should not be interrupted during the Sprint. The Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity. Based on this, which of the following is FALSE?
- What may be included in the Sprint Backlog?” (PSM I)
- Which statement best describes the Sprint Backlog as the output of the Sprint Planning?” (PSM I)
- True or False: It is mandatory that the product increment be released to production at the end of each Sprint.