Understanding the Sprint Backlog: Key Components
In Scrum, the Sprint Backlog is a critical artifact that helps guide the Developers’ work during the Sprint. Understanding what can be included in the Sprint Backlog is essential for effective Sprint planning and execution. This topic is often tested in the PSM I exam.
Exam Question
What may be included in the Sprint Backlog?
(choose the best answer)
- A. Tests.
- B. Use Cases.
- C. Tasks.
- D. User Stories.
- E. Any of the above (or others) which are a decomposition of the selected Product Backlog items.
Correct Answer
E. Any of the above (or others) which are a decomposition of the selected Product Backlog items.
Explanation
Why E is Correct
E. Any of the above (or others) which are a decomposition of the selected Product Backlog items: The Sprint Backlog is a detailed plan for achieving the Sprint Goal and includes a list of tasks and activities required to deliver the increment. It is composed of various elements such as tasks, user stories, tests, and use cases, all of which are necessary to complete the Product Backlog items selected for the Sprint. The flexibility to include different types of items helps the Developers organize their work and ensure that all aspects of the Product Backlog items are addressed.
Key Points
- Decomposition of Product Backlog Items: The Sprint Backlog contains all the work required to meet the Sprint Goal, which includes decomposing the Product Backlog items into actionable tasks.
- Detailed Plan: The Sprint Backlog serves as a roadmap for the Developers, detailing the steps needed to deliver a potentially shippable increment by the end of the Sprint.
- Dynamic and Evolving: The Sprint Backlog can evolve as more is learned during the Sprint, allowing the team to adapt and refine their approach.
Responsibilities in Scrum
- Product Owner: Ensures the Product Backlog is ordered and refined to maximize value and align with the team’s capacity.
- Scrum Master: Facilitates Scrum events and helps remove impediments but does not manage the Sprint Backlog directly.
- Developers: Own the Sprint Backlog, update it as necessary, and ensure all work aligns with the Sprint Goal.
Relevance to the PSM I Exam
Understanding what can be included in the Sprint Backlog is crucial for the PSM I exam. It highlights the importance of adaptability, continuous planning, and maintaining a clear focus on the Sprint Goal.
Conclusion
In summary, the Sprint Backlog is a dynamic artifact that can include various elements such as tasks, user stories, tests, and use cases. This flexibility allows the team to adapt and meet the Sprint Goal effectively while maintaining creativity, quality, and productivity.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- Which statement best describes the Sprint Backlog as the output of the Sprint Planning?” (PSM I)
- True or False: It is mandatory that the product increment be released to production at the end of each Sprint.
- For the purpose of transparency, when does Scrum say a valuable and useful Increment must be available?
- True or False: An Increment must be released to customers or users at the end of each Sprint.” (PSM I)
- When many Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint?” (PSM I)