Answering: “Why does the Product Owner want the Developers to adhere to its Definition of Done?”

Why does the Product Owner want the Developers to adhere to its Definition of Done?
(choose the best answer)
A. To predict the team’s productivity over time.
B. To know what the team will deliver over the next three Sprints.
C. To be able to reprimand the team when they don’t meet their velocity goal for the Sprint.
D. To have complete transparency into what has been done at the end of each Sprint.

Answering: “Why does the Product Owner want the Developers to adhere to its Definition of Done?” Read More »

Answering: “During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?”

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
(choose the best answer)
A. When the Product Owner identifies new work.
B. When the Scrum Master has time to enter it.
C. During the Daily Scrum after the Developers approve it.
D. As soon as possible after it is identified.

Answering: “During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?” Read More »