Customer satisfaction should be measured frequently. A fixed calendar like annual or quarterly is too slow for empirical work, and a daily survey is rarely the right default.
Exam Question
How often should customer satisfaction be measured?
(choose the best answer)
A. Annually.
B. Quarterly.
C. Daily.
D. Frequently.
Correct Answer
D. Frequently.
Why This Is the Correct Answer
Empiricism depends on frequent inspection so that a team can adapt before small problems grow. Customer satisfaction is one of the key signals of value. Scrum.org’s Evidence-Based Management guide lists it as a measure of current value. If it is only checked once a year or once a quarter, the team may spend many Sprints building in the wrong direction before anyone notices. “Frequently” leaves room for each product and context to choose a sensible rhythm, such as after each release or through continuous feedback channels. The point is that measurement keeps pace with delivery.
Why the Other Options Are Wrong
A. Annually. A yearly measure gives far too few chances to inspect and adapt. Many Sprints of work could go in the wrong direction.
B. Quarterly. Better than yearly, but still a fixed and slow cycle that may not match how often the team delivers.
C. Daily. Daily measurement is rarely practical or meaningful for satisfaction. The question asks for the best general guidance, which is frequent measurement fitted to context.
Exam Tip
When options mix fixed intervals with a word like “frequently” or “continuously”, Scrum.org questions usually favour the flexible word that supports empiricism.
Key Takeaways
- Customer satisfaction is a key measure of value.
- Frequent measurement lets the team adapt sooner.
- The right rhythm depends on the product, not a fixed calendar.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- Why is it important that there is only one Product Owner per product?” (PSM I)
- True or False: Scrum does NOT have a role called “project manager.
- Who should know the most about the progress toward the Product Goal?” (PSM I)
- During the Daily Scrum, the Scrum Master’s role is to:
- What is the timebox for the Sprint Review?” (PSM I)