Answering: “Eight months ago your company started development of a new platform consisting of several components and systems. You are the Scrum Master on the team building the “core” application of the platform; your application connects all other systems.”

Eight months ago your company started development of a new platform consisting of several components and systems. You are the Scrum Master on the team building the “core” application of the platform; your application connects all other systems.
The Scrum Teams work in monthly Sprints, and the team is expected to deliver all functionality in three Sprints. Recently the team’s progress was slowed down because of changes to interfaces of other components that you integrate with, as well as unavailability of the program’s testing infrastructure. The program manager is extremely upset and angry when they find out that the team will need two more Sprints. The project managers of the other components confirm their adherence to the expected date.
As a Scrum Master, what could you do to help the Product Owner?
(choose the best answer)
A. You suggest working with the program manager and the project managers of the other systems on the ordering and the value of your open Product Backlog items to redefine the possible delivery date.
B. You shorten your Sprints to be ready sooner.
C. You inform the program manager that there is a way. You remove all items from the Product Backlog for which development is forecasted to be beyond the expected date. These are likely to be low value anyhow.
D. You calculate how many additional developers it would take to increase velocity in order to make the original date. You inform the program manager of the additional budget for these developers. This would then allow making the expected date.

Answering: “Eight months ago your company started development of a new platform consisting of several components and systems. You are the Scrum Master on the team building the “core” application of the platform; your application connects all other systems.” Read More »

Answering: “Which two statements are the most accurate in regards to scaling Scrum for large projects that require multiple Scrum Teams?”

Which two statements are the most accurate in regards to scaling Scrum for large projects that require multiple Scrum Teams?
(choose the best two answers)
A. A person focusing on the Sprint Backlog of a single Scrum Team is often more productive than that same person working on multiple Scrum Teams at the same time.
B. A well-structured Product Backlog can minimize and often eliminate Developers working on multiple Scrum Teams during a Sprint.
C. A Product Owner must work full time on a single Scrum Team.
D. Customizing the core Scrum framework is necessary to be successful with Scrum at large scale.

Answering: “Which two statements are the most accurate in regards to scaling Scrum for large projects that require multiple Scrum Teams?” Read More »

Answering: “Respect is one of the five Scrum values. Which statements demonstrate respectful behavior in the Scrum Team?”

Respect is one of the five Scrum values. Which statements demonstrate respectful behavior in the Scrum Team?
(choose the best three answers)
A. Respect sponsors by not building features with low business value.
B. Respect people, their experience, diversity, and differences in opinion.
C. Respect stakeholder expectations that Scrum Teams will meet their forecast.
D. Respect the Product Owner by letting them change the Sprint Goal during the Sprint.
E. Respect the accountabilities of the Scrum Team members.

Answering: “Respect is one of the five Scrum values. Which statements demonstrate respectful behavior in the Scrum Team?” Read More »

Answering: “Which two options describe how project budgeting and financial forecasting work in Scrum?”

Which two options describe how project budgeting and financial forecasting work in Scrum?
(choose the best two answers)
A. It’s ideally revisited as frequently as each Sprint to ensure value is being delivered for the investment spent.
B. Several Sprints may be funded as a single release, with the result of each Sprint being releasable software.
C. The only funding is for the run cost (time and materials) of the Scrum Teams, so no budgeting process is needed.
D. Scrum does not align with traditional accounting practices. The financial department needs to be given a fixed cost per Sprint per team.

Answering: “Which two options describe how project budgeting and financial forecasting work in Scrum?” Read More »