Answering: “Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have the tools and environment to completely finish each selected Product Backlog item?”
Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have the tools and environment to completely finish each selected Product Backlog item?
(choose the best two answers)
A. Refocus the current Sprint on establishing the Scrum Team’s environment instead of delivering an Increment.
B. Have the Scrum Team establish a Definition of Done that is actually possible to achieve given the current circumstances.
C. Declare the Scrum Team not ready for Scrum.
D. Encourage the Product Owner to accept partially done Increments until the situation improves.
E. Coach the Scrum Team to improve its skills, tools and environment over time and adjust the Definition of Done accordingly.