The Scrum Master should start facilitating Sprint Retrospectives that the team finds productive and useful. Self-management does not allow a team to drop a Scrum event.
Exam Question
A Scrum Master is introducing Scrum to a new Team. The Team has decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take? (choose the best answer)
- A. Begin facilitating productive and useful Sprint Retrospectives.
- B. Consult with the Product Owner to see how they feel about the situation.
- C. Call a meeting between the Scrum Team and senior management.
- D. Comply with the decision of the self-managing team.
Correct Answer
A. Begin facilitating productive and useful Sprint Retrospectives.
Why This Is the Correct Answer
The Scrum Guide says the Scrum Master “is accountable for establishing Scrum as defined in the Scrum Guide.” The Sprint Retrospective is a required event, and its purpose is to plan ways to increase quality and effectiveness. A new team often feels it is unnecessary because it has not yet seen one done well. The best response is to show the value: run Retrospectives that surface real problems and lead to improvements the team notices. The Guide also lists ensuring that all Scrum events take place and are positive and productive among the Scrum Master’s services. Once the team sees results, it will rarely want to skip the event again.
Why the Other Options Are Wrong
B. Consult with the Product Owner. The Product Owner has no authority to remove events either. This delays action and shifts the issue away from the Scrum Master.
C. Call a meeting with senior management. Escalating is premature. The Scrum Master can address this directly through coaching and facilitation.
D. Comply with the decision of the self-managing team. Self-management covers how the team does its work within Scrum. Dropping an event means the team is no longer using Scrum.
Exam Tip
When a team wants to skip an event, the Scrum Master answer that teaches by making the event valuable usually beats answers that comply or escalate.
Key Takeaways
- The Sprint Retrospective is mandatory in Scrum.
- Show value by running good events rather than lecturing.
- Self-management works inside the Scrum framework.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario.” (PSM I)
- Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the quality of the product. What are two good options for the Scrum Master?
- What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which agile practices to apply?
- The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?” (PSM I)
- During Sprint Planning the Product Owner and the Developers are unable to reach an understanding about the highest order Product Backlog items. Because of this, the Developers are unable to determine how many Product Backlog items they can forecast for the upcoming Sprint. However, the Product Owner and the Developers are able to agree on a Sprint Goal.