False. The Developers can select an item in Sprint Planning without complete acceptance criteria. Scrum only asks that items be refined enough to be done within one Sprint.
Exam Question
True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.
- A. True
- B. False
Correct Answer
B. False
Why This Is the Correct Answer
The Scrum Guide says items “that can be Done by the Scrum Team within one Sprint are deemed ready for selection in a Sprint Planning event.” Acceptance criteria are not part of Scrum, and in complex work they could never be truly complete before the work starts. The Product Owner and Developers keep clarifying details during the Sprint, and “scope may be clarified and renegotiated with the Product Owner as more is learned.”
Why the Other Options Are Wrong
A. True Requiring complete criteria up front is a gate the Scrum Guide does not have. It also suggests a hand-off from Product Owner to Developers, when Scrum expects them to work out details together.
Exam Tip
This question has a twin about “clear and unambiguous” acceptance criteria. Both are false for the same reason: Scrum never requires acceptance criteria.
Key Takeaways
- Ready for selection means it can be done within one Sprint.
- Acceptance criteria are optional and emerge over time.
- Details are clarified collaboratively during the Sprint.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- In order to maximize the value of the product, a Product Owner needs awareness of the following:
- How small should a “ready” Product Backlog item be?” (PSPO I)
- True or False: Product Owners must create clear and unambiguous acceptance criteria for each Product Backlog item before it may be selected in Sprint Planning.
- True or False: A Product Owner with multiple teams working on one product should maintain separate Product Backlogs for each team.
- Which metrics will help a Product Owner determine if a product is delivering value?