False. Scrum does not require acceptance criteria, let alone clear and unambiguous ones, before an item can be selected. Items need to be understood well enough to be done within one Sprint.
Exam Question
True or False: Product Owners must create clear and unambiguous acceptance criteria for each Product Backlog item before it may be selected in Sprint Planning.
- A. True
- B. False
Correct Answer
B. False
Why This Is the Correct Answer
The Scrum Guide says that “Product Backlog items that can be Done by the Scrum Team within one Sprint are deemed ready for selection in a Sprint Planning event.” It does not mention acceptance criteria. Many teams find acceptance criteria helpful, but they are a complementary practice. Details also keep emerging during the Sprint, and the Guide expects scope to be “clarified and renegotiated with the Product Owner as more is learned.”
Why the Other Options Are Wrong
A. True This turns an optional practice into a rule and assumes everything can be known up front. In complex work, items only need enough clarity to start, and the Product Owner keeps clarifying during the Sprint.
Exam Tip
True/False questions with “must” in them are usually false on Scrum.org exams, especially when the “must” is a practice the Scrum Guide never mentions.
Key Takeaways
- An item is ready when the team can complete it within one Sprint.
- Acceptance criteria are optional and need not be complete up front.
- Clarification continues throughout the Sprint.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- True or False: A Product Owner with multiple teams working on one product should maintain separate Product Backlogs for each team.
- Which metrics will help a Product Owner determine if a product is delivering value?
- True or False: A Product Owner can measure success by an increase in the team’s velocity.
- True or False: All planned work to be done by the Developers must ultimately originate from the Product Backlog.
- True or False: The Product Owner must write all of the Product Backlog items (eg users stories, requirements, etc) on the Product Backlog before handing them over to the Scrum Team.