False. One product has one Product Backlog, even when several teams work on it. Separate backlogs per team would fragment ordering and hide dependencies.
Exam Question
True or False: A Product Owner with multiple teams working on one product should maintain separate Product Backlogs for each team.
- A. True
- B. False
Correct Answer
B. False
Why This Is the Correct Answer
The Scrum Guide calls the Product Backlog “the single source of work undertaken by the Scrum Team.” When a product needs several Scrum Teams, the Guide says they should share the same Product Goal, Product Backlog and Product Owner. One ordered list lets the Product Owner make clear trade-offs across all the work, and it lets every team see what the others are doing. Teams can still tag items or view filtered slices to plan their Sprints, but there is only one backlog underneath. Separate backlogs would force the Product Owner to juggle competing orders and would make it harder to produce one integrated Increment.
Why the Other Options Are Wrong
A. True Separate backlogs per team break the single ordered list, create competing priorities and make integration harder.
Exam Tip
For multi-team setups, remember the triple: one Product Owner, one Product Backlog and one Product Goal per product. Anything per team is a trap.
Key Takeaways
- A product has a single Product Backlog.
- Multiple teams pull from the same ordered list.
- One backlog makes trade-offs and dependencies visible.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- Which metrics will help a Product Owner determine if a product is delivering value?
- True or False: A Product Owner can measure success by an increase in the team’s velocity.
- True or False: All planned work to be done by the Developers must ultimately originate from the Product Backlog.
- True or False: The Product Owner must write all of the Product Backlog items (eg users stories, requirements, etc) on the Product Backlog before handing them over to the Scrum Team.
- What three things might a Scrum Product Owner focus on to ensure the product delivers value?