Understanding Flow-Based Systems in Scrum with Kanban
In a flow-based system, the focus is on limiting the amount of value-generating work items rather than the number of tasks.
Exam Question
True or False: In a flow-based system, the number of tasks is not necessarily limited, rather the amount of value-generating work items is limited.
A. True
B. False
Correct Answer
A. True
Explanation
Correct Answer
A. True:
In a flow-based system like Scrum with Kanban, the emphasis is on managing and limiting the Work in Progress (WIP) for value-generating work items, rather than simply limiting the number of tasks. The idea is to focus on completing fewer, more valuable work items at a time, ensuring that these items move through the workflow smoothly and efficiently. By limiting the amount of value-generating work in progress, teams can maintain a steady flow, reduce bottlenecks, and deliver value more consistently.
Key Points on Flow-Based Systems
- Focus on Value: The primary goal is to maximize the flow of value through the system. Limiting WIP for value-generating work items helps ensure that the most important work is completed efficiently.
- Task Management: While tasks are necessary to complete work items, the system does not typically limit the number of tasks directly. Instead, it limits the broader work items that contribute directly to delivering value.
- Efficient Workflow: Limiting WIP at the work item level helps to maintain an efficient workflow, reducing the likelihood of work items being stuck in progress and ensuring a smoother path to completion.
Relevance to the PSK I Exam
Understanding the principles of flow-based systems in Scrum with Kanban, particularly the focus on limiting value-generating work items rather than tasks, is essential for the PSK I exam. It demonstrates knowledge of how to manage work effectively in a flow-based system.
Key Takeaways
- In a flow-based system, the focus is on limiting the amount of value-generating work in progress, not the number of tasks.
- This approach helps to maintain a steady flow of work and ensures that the most valuable items are completed efficiently.
- Limiting WIP at the work item level is key to maximizing value delivery in a flow-based system.
Conclusion
In flow-based systems like Scrum with Kanban, the emphasis is on limiting the amount of value-generating work items rather than the number of tasks. This focus ensures that teams can deliver value consistently and efficiently.

Get ready for the official PSK I exam
115 PSK I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 45 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSK I exam fee ($200) is paid separately to Scrum.org.
More PSK I exam questions
- True or False: The main role of WIP Aging is to help identify flow bottlenecks; where work may be impeded or constrained.
- Little’s Law is extremely valuable for directly predicting the future because it gives us a measure of what happened in the past?
- The team needs to work on a high priority urgent unplanned item, but they are at their WIP limit.
- Who owns the Kanban board in the Sprint Backlog?
- True or False: Cycle time is a direct leading indicator for the length of the Scrum Team’s feedback loop for a product backlog item.