Ownership of the Kanban Board in the Sprint Backlog
In Scrum with Kanban, the Kanban board is a tool that helps visualize work in progress within the Sprint Backlog. Understanding who owns and manages this board is essential for effective workflow management.
Exam Question
Who owns the Kanban board in the Sprint Backlog?
(Choose the best answer)
A. The Product Owner
B. The Scrum Master
C. The Developers
D. The Scrum Team
Correct Answer
C. The Developers
Explanation
Correct Answer
C. The Developers:
The Kanban board in the Sprint Backlog is primarily owned and managed by the Developers. In Scrum, the Developers are responsible for organizing and managing the work needed to achieve the Sprint Goal. This includes using tools like the Kanban board to visualize and track the flow of work within the Sprint. While the Product Owner defines the “what” (the Product Backlog items) and the Scrum Master facilitates the process, it is the Developers who determine “how” the work will be carried out and tracked during the Sprint.
Key Points on Kanban Board Ownership
- Developers’ Responsibility: The Developers are responsible for managing the Sprint Backlog and ensuring that work progresses smoothly towards the Sprint Goal. The Kanban board is a tool that helps them do this effectively.
- Visualization of Work: The Kanban board provides transparency into the state of work in progress, helping Developers monitor flow, identify bottlenecks, and make informed decisions about how to proceed.
- Collaboration: While the Developers own the board, the entire Scrum Team (including the Product Owner and Scrum Master) collaborates to ensure the work is aligned with the Sprint Goal and that any impediments are addressed.
Relevance to the PSK I Exam
Understanding who owns the Kanban board within the Sprint Backlog is crucial for the PSK I exam. This knowledge demonstrates the ability to manage and visualize work effectively in a Scrum with Kanban environment.
Key Takeaways
- The Kanban board in the Sprint Backlog is owned and managed by the Developers, who are responsible for organizing and tracking work during the Sprint.
- The board is a tool for visualizing work in progress, helping Developers ensure a smooth flow towards the Sprint Goal.
- While the Developers own the board, the entire Scrum Team collaborates to achieve the Sprint Goal and address any challenges that arise.
Conclusion
In Scrum with Kanban, the Kanban board within the Sprint Backlog is owned by the Developers. They use this tool to manage and visualize their work, ensuring progress towards the Sprint Goal.

Get ready for the official PSK I exam
115 PSK I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 45 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSK I exam fee ($200) is paid separately to Scrum.org.
More PSK I exam questions
- True or False: Cycle time is a direct leading indicator for the length of the Scrum Team’s feedback loop for a product backlog item.
- True or False: The purpose of a Scrum Team’s Service Level Expectation (SLE) is to allow teams to give each PBI a commitment to a due date as part of Sprint Planning.
- True or False: Scrum Events, Roles, Artifacts, and Rules are impacted when using Scrum with Kanban. For example, having a clear indicator of the age of active Sprint Backlog items may be beneficial during Daily Scrum, thereby positively impacting the decisions about how to Inspect and Adapt in the next day.
- You still need a Scrum Master when applying Kanban practices in the Scrum framework.
- Which of the following are lagging indicator metrics?