Understanding Cycle Time and Feedback Loops in Scrum with Kanban
Cycle time is an important metric in Kanban, but its role as a leading indicator for the length of the Scrum Team’s feedback loop needs careful consideration.
Exam Question
True or False: Cycle time is a direct leading indicator for the length of the Scrum Team’s feedback loop for a product backlog item.
A. True
B. False
Correct Answer
B. False
Explanation
Correct Answer
B. False:
Cycle time is a measure of how long it takes for a work item to move from the start of work to its completion. While it provides valuable insights into how efficiently work is being processed, it is considered a lagging indicator because it reflects what has already happened. Therefore, cycle time is not a direct leading indicator for the length of the feedback loop. Leading indicators are metrics that can provide insights into what might happen in the future, such as Work Item Age or WIP limits, which help teams predict and manage workflow before work is completed.
Key Points on Cycle Time and Feedback Loops
- Cycle Time as a Lagging Indicator: Cycle time measures the time taken to complete work but does not predict how long current or future items will take.
- Feedback Loop Length: The length of the feedback loop is more closely associated with leading indicators like Work Item Age, which tracks how long an item has been in progress and signals when intervention might be needed.
- Predictive Metrics: While cycle time provides valuable historical data, it does not serve as a predictive tool for managing the length of feedback loops or for forecasting future performance.
Relevance to the PSK I Exam
Understanding the difference between leading and lagging indicators, particularly in the context of cycle time and feedback loops, is important for the PSK I exam. It demonstrates knowledge of how to use metrics effectively in a Scrum with Kanban environment.
Key Takeaways
- Cycle time is a lagging indicator, reflecting how long work has taken, not predicting future feedback loop lengths.
- Leading indicators like Work Item Age are more effective for managing and predicting the length of feedback loops.
- Effective use of metrics requires understanding their role in both historical analysis and future prediction.
Conclusion
Cycle time is a valuable metric for understanding past performance, but it is not a leading indicator for predicting the length of the Scrum Team’s feedback loop.

Get ready for the official PSK I exam
115 PSK I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 45 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSK I exam fee ($200) is paid separately to Scrum.org.
More PSK I exam questions
- True or False: The purpose of a Scrum Team’s Service Level Expectation (SLE) is to allow teams to give each PBI a commitment to a due date as part of Sprint Planning.
- True or False: Scrum Events, Roles, Artifacts, and Rules are impacted when using Scrum with Kanban. For example, having a clear indicator of the age of active Sprint Backlog items may be beneficial during Daily Scrum, thereby positively impacting the decisions about how to Inspect and Adapt in the next day.
- You still need a Scrum Master when applying Kanban practices in the Scrum framework.
- Which of the following are lagging indicator metrics?
- When is the most appropriate time for Scrum Teams practicing professional Scrum with Kanban to inspect and adapt their Work in Progress (WIP) Limits?