Starting a Sprint Without a Complete Product Backlog
The flexibility in Scrum allows for iterative and incremental development, which means that a complete and exhaustive Product Backlog is not required before starting the first Sprint. Having a complete and exhaustive Product Backlog can generate waste, and not everything can be known upfront when working on complex problems.
Exam Question
True or False: A first Sprint can start before the Product Owner has a complete and exhaustive Product Backlog in place.
- A. True
- B. False
Correct Answer
A. True
Explanation
Why A is Correct
- True:
- Scrum emphasizes an iterative and incremental approach to development. It is not necessary to have a complete and exhaustive Product Backlog to start the first Sprint. The Product Backlog is a living artifact that evolves as more is learned about the product and its requirements. The Product Owner can add and refine items in the Product Backlog continuously throughout the project. This approach allows the team to start working and delivering value early, even as the full scope of work is still being defined. Having a complete and exhaustive Product Backlog can generate waste and not everything can be known upfront when working on complex problems.
Responsibilities in Scrum
- Product Owner: Responsible for managing the Product Backlog and ensuring it is transparent, visible, and understood. The Product Owner continuously refines and updates the backlog as more information becomes available.
- Scrum Master: Facilitates the Scrum process, supports the Product Owner and Developers, and ensures Scrum practices are followed.
- Developers: Work on the highest ordered items in the Product Backlog and deliver valuable Increments each Sprint.
Relevance to the PSPO I Exam
Understanding that Scrum supports starting work without a complete Product Backlog is crucial for the PSPO I exam. This concept aligns with the principles of iterative and incremental development, allowing teams to begin delivering value early and continuously refine their understanding of the product.
Key Takeaways
- Iterative Development: Scrum supports starting with an incomplete Product Backlog, allowing for continuous refinement and evolution of requirements.
- Value Delivery: Starting work early enables the team to deliver value incrementally and receive feedback that informs future work.
Conclusion
In Scrum, it is not necessary to have a complete and exhaustive Product Backlog before starting the first Sprint. This flexibility allows teams to begin delivering value early and refine the product requirements iteratively. Having a complete and exhaustive Product Backlog can generate waste and not everything can be known upfront when working on complex problems.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- How can a Product Owner use time-boxed Sprints to obtain feedback from users and the market?
- How important is it for a Product Owner to order Product Backlog items by value points?
- True or False: The Sprint Review is the only time at which stakeholder feedback is taken into account.
- What two things should be done if the Product Owner is unavailable?
- When can the Product Backlog be updated?