A cone of uncertainty helps a Product Owner in a complex environment forecast how much scope is likely to be done over a number of Sprints. It shows a range that widens the further out the forecast goes, rather than a single date or number.
Exam Question
A “cone of uncertainty” can be used to do what?
(choose the best answer)
A. Rapidly identify and prioritize all uncertainties.
B. Represent the relative level of difficulty for predicting the velocity of individual team members.
C. Help a Product Owner, working in a complex environment, forecast the scope of work likely to be done during a certain number of Sprints.
D. Determine whether to cut quality, similar to the “Iron Triangle” of project management.
Correct Answer
C. Help a Product Owner, working in a complex environment, forecast the scope of work likely to be done during a certain number of Sprints.
Why This Is the Correct Answer
The cone of uncertainty is a forecasting aid, not a Scrum artifact. It plots a range of outcomes that is narrow in the near term and broad further out. A Product Owner can use it with past data, such as how much the team typically finishes per Sprint, to say what scope is likely, possible and unlikely by a given point. The Scrum Guide reminds us that in complex environments “what will happen is unknown,” and that forecasting practices do not replace empiricism. The cone keeps that uncertainty visible to stakeholders.
Why the Other Options Are Wrong
A. Rapidly identify and prioritize all uncertainties. The cone shows how uncertain a forecast is. It does not list or order specific uncertainties.
B. Show how hard it is to predict each team member’s velocity. Scrum does not track individual velocity. Forecasts are about what the team delivers.
D. Decide whether to cut quality, like the Iron Triangle. Quality does not decrease in Scrum. The cone is about forecast ranges, not trade-offs on quality.
Exam Tip
When a forecasting tool appears in a PSPO question, pick the answer that uses ranges and empirical data. Answers about cutting quality or tracking individuals are distractors.
Key Takeaways
- The cone of uncertainty expresses forecasts as widening ranges.
- Product Owners use it to forecast likely scope over several Sprints.
- Forecasting tools support empiricism but never replace it.

Get ready for the official PSPO II exam
120 PSPO II practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 40 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO II exam fee ($250) is paid separately to Scrum.org.
More PSPO II exam questions
- An analysis of the customers for your product reveals that you have several different kinds of customers that use your product in very different ways. What should you do with this insight?
- If Product Backlog refinement is needed, when is the ideal time for refinement to take place and who should participate?” (PSPO II)
- Which of the following are required by Scrum?” (PSPO II)
- As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?” (PSPO II)
- The Developers inform the Product Owner during the Sprint that they are not likely to complete everything they forecasted. What would you expect a Product Owner to do?