Answering: “Which questions does the Scrum Guide suggest all Developers answer at the Daily Scrum?”

Which questions does the Scrum Guide suggest all Developers answer at the Daily Scrum?
(choose the best answer)
A. What work did I do yesterday to help the team achieve its goal?
B. What work am I going to do today to help the team achieve its goal?
C. What impediments are in my way or in the way of the team?
D. How many hours did I spend on the project yesterday?
E. All of the above.
F. None of the above.

Answering: “Which questions does the Scrum Guide suggest all Developers answer at the Daily Scrum?” Read More »

Answering: “The leading revenue-producing product in your portfolio has:”

The leading revenue-producing product in your portfolio has:
– high Current Value
– low Unrealized Value
The product has been losing customers for several years and revenues are down. Using those two data points and options below, what is the first action you should take?
(choose the best answer)
A. Drop the price for the product to attract new customers.
B. Maintain the product, but begin reducing investment; seek other opportunities for future growth.
C. Increase marketing for the product.
D. Increase investment in the product to create greater interest and bring old customers back.

Answering: “The leading revenue-producing product in your portfolio has:” Read More »

Answering: “A “cone of uncertainty” can be used to do what?”

A “cone of uncertainty” can be used to do what?
(choose the best answer)
A. Rapidly identify and prioritize all uncertainties.
B. Represent the relative level of difficulty for predicting the velocity of individual team members.
C. Help a Product Owner, working in a complex environment, forecast the scope of work likely to be done during a certain number of Sprints.
D. Determine whether to cut quality, similar to the “Iron Triangle” of project management.

Answering: “A “cone of uncertainty” can be used to do what?” Read More »

Answering: “Which activities will a Product Owner likely engage in during a Sprint?”

Which activities will a Product Owner likely engage in during a Sprint?
(choose the best three answers)
A. Gather information and opinions from stakeholders.
B. Prioritize the Developers’ tasks.
C. Run the Daily Scrum.
D. Update the Sprint burndown chart.
E. Answer questions from the Developers about items in the current Sprint.
F. Rearrange Product Backlog items.

Answering: “Which activities will a Product Owner likely engage in during a Sprint?” Read More »

Answering: “If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?” (PSPO II)

If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?
(choose the best answer)
A. When all work will be completed so the Scrum Team can be released for other work.
B. When the project will be over if the Product Owner removes work that is equal in effort to any new work that is added.
C. When the work remaining will likely be completed if nothing changes on the Product Backlog or Scrum Team.
D. The evolution of the cost spent on the project.

Answering: “If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?” (PSPO II) Read More »

Answering: “You work for a large financial institution. Your products have many interdependencies: you have mobile, web, and ATM product interfaces to financial products like savings, checking, credit card, investments. When any of these financial products change, the changes ripple throughout the mobile, web, and ATM clients, and maintaining consistency is challenging. What should you do to reduce this problem?”

You work for a large financial institution. Your products have many interdependencies: you have mobile, web, and ATM product interfaces to financial products like savings, checking, credit card, investments. When any of these financial products change, the changes ripple throughout the mobile, web, and ATM clients, and maintaining consistency is challenging. What should you do to reduce this problem?
(choose the best answer)
A. Form products that are as independent as possible and let each product determine their own release plans, but ensure coordination.
B. Create a centralized, coordinated cross-product Development Plan to ensure consistency.
C. Appoint an overall Product Owner to oversee all the products.
D. Ensure that the PMO manages the inter-product dependencies.
E. All of the above.

Answering: “You work for a large financial institution. Your products have many interdependencies: you have mobile, web, and ATM product interfaces to financial products like savings, checking, credit card, investments. When any of these financial products change, the changes ripple throughout the mobile, web, and ATM clients, and maintaining consistency is challenging. What should you do to reduce this problem?” Read More »