If the forecast looks bigger than capacity during Sprint Planning, the Developers can remove or change selected Product Backlog items, or make the risk transparent to the Scrum Team, start the Sprint and watch progress closely. Overtime, hiring and cancellation are not the answer.
Exam Question
As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?
(choose the best two answers)
A. Recruit additional Developers before the work can begin.
B. The Developers ensure that the Scrum Team is aware, start the Sprint, and monitor progress.
C. The Developers work overtime during this Sprint.
D. Cancel the Sprint.
E. Remove or change selected Product Backlog items.
Correct Answer
B and E.
Why This Is the Correct Answer
Sprint Planning is collaborative. The Scrum Guide says that through discussion with the Product Owner, the Developers select items from the Product Backlog to include in the Sprint, and that selecting how much can be completed may be challenging. If the selection looks too large, the simplest fix is to change it: drop, split or swap items while keeping a coherent Sprint Goal. Alternatively, the team can start with what it has, as long as everyone knows the forecast is at risk. The Sprint Backlog is updated throughout the Sprint as more is learned, and scope can be renegotiated with the Product Owner. Either path keeps the plan honest and sustainable.
Why the Other Options Are Wrong
A. Recruit additional Developers before work begins. Adding people takes time and changes the team. It does not fix an oversized forecast for this Sprint.
C. The Developers work overtime this Sprint. Overtime is not sustainable and tends to lower quality. The Definition of Done must not suffer to meet a forecast.
D. Cancel the Sprint. Only the Product Owner can cancel a Sprint, and only when the Sprint Goal becomes obsolete. Too much work is not a reason.
Exam Tip
When the plan does not fit capacity, look for answers that adjust scope or increase transparency. Answers that add hours, add people or cancel are almost always wrong.
Key Takeaways
- The Developers decide how much work fits in the Sprint.
- Scope can be adjusted during Sprint Planning or renegotiated later.
- Overtime and cancellation do not fix an oversized forecast.

Get ready for the official PSPO II exam
120 PSPO II practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 40 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO II exam fee ($250) is paid separately to Scrum.org.
More PSPO II exam questions
- The Developers inform the Product Owner during the Sprint that they are not likely to complete everything they forecasted. What would you expect a Product Owner to do?
- When should the Product Owner update the project plan?” (PSPO II)
- What might indicate to a Product Owner that they need to work more with the Scrum Team?” (PSPO II)
- Sharing people with unique skills across multiple teams will likely result in which of the following conditions?
- Which of the following are true about the Product Owner role?