Answering: “When the Product Owner is too busy to work with all of the teams in a multi-team product development effort, which strategy will help them?”

When the Product Owner is too busy to work with all of the teams in a multi-team product development effort, which strategy will help them?
(choose the best answer)
A. Add component team Product Owners.
B. Communicate a clear Product Goal and delegate some activities to the Developers.
C. Enlist the Program Management Office to help coordinate work.
D. Hire sub-Product Owners and assign them to each Scrum Team.
E. All of the above.

Answering: “When the Product Owner is too busy to work with all of the teams in a multi-team product development effort, which strategy will help them?” Read More »

Answering: “As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?” (PSPO II)

As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?
(choose the best two answers)
A. Recruit additional Developers before the work can begin.
B. The Developers ensure that the Scrum Team is aware, start the Sprint, and monitor progress.
C. The Developers work overtime during this Sprint.
D. Cancel the Sprint.
E. Remove or change selected Product Backlog items.

Answering: “As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?” (PSPO II) Read More »

Answering: “Which of the following practices might help the Product Owner minimize waste in developing and sustaining the Product Backlog?” (PSPO II)

Which of the following practices might help the Product Owner minimize waste in developing and sustaining the Product Backlog?
(choose all that apply)
A. Only fully describe Product Backlog items near the top of the Product Backlog since they are more likely to be selected during Sprint Planning.
B. Maintain newly gathered Product Backlog items in a separate Product Backlog until they are fully understood to avoid distracting the Developers.
C. Write Product Backlog items with clearly expressed expected outcomes.
D. As Product Owner, ask the Developers to refine several important Product Backlog items.

Answering: “Which of the following practices might help the Product Owner minimize waste in developing and sustaining the Product Backlog?” (PSPO II) Read More »