Answering: “Five new Scrum Teams have been created to build one product. A few of the Developers on one of the Scrum Teams ask the Scrum Master how to coordinate their work with the other teams. What should the Scrum Master do?”

Five new Scrum Teams have been created to build one product. A few of the Developers on one of the Scrum Teams ask the Scrum Master how to coordinate their work with the other teams. What should the Scrum Master do?
(choose the best answer)
A. Teach them that it is their responsibility to work with the other teams to create an integrated Increment that is inclusive of all five team’s work.
B. Visit the five teams each day to inspect that their Sprint Backlogs are aligned.
C. Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much overlap during a Sprint.
D. Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.

Answering: “Five new Scrum Teams have been created to build one product. A few of the Developers on one of the Scrum Teams ask the Scrum Master how to coordinate their work with the other teams. What should the Scrum Master do?” Read More »

Answering: “What is the accountability of the Product Owner during Sprint 0?”

What is the accountability of the Product Owner during Sprint 0?
(choose the best answer)
A. Make sure enough Product Backlog items are refined to fill the first 3 Sprints.
B. Determine the composition of the Scrum Teams so they have the capacity to deliver the forecasted release.
C. There is no such thing as Sprint 0.
D. Gathering, eliciting and analyzing the requirements that will be inserted into the Product Backlog.

Answering: “What is the accountability of the Product Owner during Sprint 0?” Read More »

Answering: “True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.”

True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.
A. True
B. False

Answering: “True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.” Read More »