Coordinating Work Among Multiple Scrum Teams
When multiple Scrum Teams are working on the same product, coordination becomes essential to ensure a cohesive and integrated Increment. This article explores the role of the Scrum Master in facilitating this coordination.
Exam Question
Five new Scrum Teams have been created to build one product. A few of the Developers on one of the Scrum Teams ask the Scrum Master how to coordinate their work with the other teams. What should the Scrum Master do?
(choose the best answer)
A. Teach them that it is their responsibility to work with the other teams to create an integrated Increment that is inclusive of all five team’s work.
B. Visit the five teams each day to inspect that their Sprint Backlogs are aligned.
C. Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much overlap during a Sprint.
D. Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.
Correct Answer
A. Teach them that it is their responsibility to work with the other teams to create an integrated Increment that is inclusive of all five team’s work.
Explanation
Correct Answer
A. Teach them that it is their responsibility to work with the other teams to create an integrated Increment that is inclusive of all five team’s work:
Scrum promotes self-management and cross-team collaboration. The Developers on each Scrum Team are responsible for coordinating with other teams to ensure that their work integrates into a single, cohesive Increment by the end of each Sprint. Because they are the ones doing the work, they have the best understanding of what needs to be done and how to integrate their work with each other.
Incorrect Answers
B. Visit the five teams each day to inspect that their Sprint Backlogs are aligned: This approach undermines the self-managing nature of Scrum Teams. The Scrum Master should facilitate coordination rather than micromanage the teams.
C. Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much overlap during a Sprint: While the Product Owner is responsible for ordering the Product Backlog, the focus should be on maximizing value rather than solely avoiding overlap. Coordination should be a collaborative effort among the Scrum Teams.
D. Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint: This contradicts the principle of self-management. Each Scrum Team should manage its own Sprint Backlog while coordinating with other teams as needed.
Responsibilities in Scrum
- Product Owner: The Product Owner is responsible for maximizing the value of the product by ordering the Product Backlog. They ensure that the work aligns with the product vision and stakeholder needs.
- Scrum Master: The Scrum Master facilitates coordination among Scrum Teams, ensuring that they work together to deliver an integrated Increment. They coach the teams on effective collaboration and self-management.
- Developers: The Developers are responsible for creating an integrated Increment. They collaborate with other teams to ensure their work aligns and integrates well with the work of other Scrum Teams. Because they are the ones doing the work, they are the ones that have the best understanding of what needs to be done and how to integrate their work with each other.
Relevance to the PSPO I Exam
Understanding the coordination among multiple Scrum Teams is crucial for the PSPO I exam. This knowledge ensures that candidates appreciate the importance of collaboration, self-management, and delivering integrated Increments in a multi-team environment.
Key Takeaways
- Scrum Teams are self-managing and responsible for coordinating their work with other teams.
- The Product Owner orders the Product Backlog to maximize value, not just to avoid overlap.
- The Scrum Master facilitates coordination and ensures effective collaboration among teams.
- Developers work collaboratively to deliver an integrated Increment each Sprint.
Conclusion
Effective coordination among multiple Scrum Teams is essential for delivering integrated Increments. By fostering self-management and collaboration, Scrum Teams can ensure that their work aligns and integrates well, resulting in a cohesive product.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- Which of the following is a Developer accountable for?” (PSPO I)
- During the Sprint Retrospective a Scrum Team has identified several high priority process improvements. Which of the following statements is most accurate?” (PSPO I)
- Why is the Daily Scrum held at the same time and same place?” (PSPO I)
- The Product Owner is the person who will be held accountable if a product does not achieve its goals or deliver value. Does this mean that the Product Owner has final say over the Definition of Done?” (PSPO I)
- If Product Backlog refinement is needed, when is the ideal time for refinement to take place and who should participate?” (PSPO I)