Answering: “In the middle of the Sprint, the customer decides that there are two new features she wants. The Product Owner could:”

In the middle of the Sprint, the customer decides that there are two new features she wants. The Product Owner could:
(choose the best two answers)
A. Ask the Developers to consider whether they can add these features to the current Sprint without endangering the Sprint Goal.
B. Have the Scrum Master add these features to the current Sprint.
C. Add these features to the Product Backlog.
D. Introduce these features at the next Daily Scrum.

Answering: “In the middle of the Sprint, the customer decides that there are two new features she wants. The Product Owner could:” Read More »

Answering: “Which two things should the Scrum Team do during the first Sprint?”

Which two things should the Scrum Team do during the first Sprint?
(choose the best two answers)
A. Create an Increment of potentially releasable software.
B. Analyze, describe, and document the requirements for the subsequent Sprints.
C. Develop at least one piece of functionality.
D. Make up a plan for the rest of the project.
E. Define the major product features and a release plan architecture.

Answering: “Which two things should the Scrum Team do during the first Sprint?” Read More »