Answering: “Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?” (PSM I)

Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?
(choose the best answer)
A. Lead the discussions.
B. Make sure that all 3 questions have been answered by each member of the team.
C. Keep track of whether each Developer has a chance to speak.
D. Teach the Developers to keep the Daily Scrum within the 15 minutes.
E. All of the above.

Answering: “Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?” (PSM I) Read More »

Answering: “The Product Owner is not collaborating with the Developers during the Sprint. What are two valuable actions for a Scrum Master to take?”

The Product Owner is not collaborating with the Developers during the Sprint. What are two valuable actions for a Scrum Master to take?
(choose the best two answers)
A. Coach the Product Owner in the values of Scrum and incremental delivery.
B. Bring up the problem in the Sprint Retrospective.
C. Nominate a proxy Product Owner.
D. Stop the Sprint, send the Product Owner to a course and restart.
E. Inform the Product Owner’s functional manager.

Answering: “The Product Owner is not collaborating with the Developers during the Sprint. What are two valuable actions for a Scrum Master to take?” Read More »