Answering: “As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do?” (PSM I)
As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do?
(choose the best answer)
A. Reduce the Definition of Done and get all of the Product Backlog items done by the new definition.
B. As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.
C. Find another Scrum Team to give the excess work to.
D. Inform the Product Owner at the Sprint Review, but prior to the demonstration.