Answering: “The Scrum team has been using the Daily Scrum to report Sprint progress to the Product Owner, because the Product Owner wants to track what every Developer is working on every day. What is the best thing for the Scrum Master to do?”

The Scrum team has been using the Daily Scrum to report Sprint progress to the Product Owner, because the Product Owner wants to track what every Developer is working on every day. What is the best thing for the Scrum Master to do?
(choose the best answer)
A. Ask the Product Owner to stop attending the Daily Scrum.
B. Coach the Product Owner and Developers on the purpose of Scrum events and let them figure out how to deal with this situation.
C. Nothing. The Product Owner can continue to track progress at the Daily Scrum.
D. Start attending the Daily Scrum so that whenever the Developers have a conflict with the Product Owner, the Scrum Master can resolve the conflict.

Answering: “The Scrum team has been using the Daily Scrum to report Sprint progress to the Product Owner, because the Product Owner wants to track what every Developer is working on every day. What is the best thing for the Scrum Master to do?” Read More »

Answering: “A Scrum Master colleague of yours wants some guidance on what to do in the following situation. During the Daily Scrum, one Scrum Team member, who is a key central figure in the organization, drags on and on about things which actually are interesting but not relevant for the Daily Scrum, day after day. What are two suggestions you offer the Scrum Master?”

A Scrum Master colleague of yours wants some guidance on what to do in the following situation. During the Daily Scrum, one Scrum Team member, who is a key central figure in the organization, drags on and on about things which actually are interesting but not relevant for the Daily Scrum, day after day. What are two suggestions you offer the Scrum Master?
(choose the best two answers)
A. You suggest coaching the Developers to help them find a way to solve the problem, and own the solution.
B. You contact the team member’s Line Manager and raise this as an impediment to the Manager, and ask that they resolve this matter.
C. You suggest using a timer, to limit the time each person can speak at the Daily Scrum.
D. You suggest passing a token around. The person holding the token has the floor to speak for an allotted amount of time.
E. You suggest taking the person aside and asking them what they believe the key outcomes are for the Daily Scrum. Effectively coaching them to help create focus during the Daily Scrum.

Answering: “A Scrum Master colleague of yours wants some guidance on what to do in the following situation. During the Daily Scrum, one Scrum Team member, who is a key central figure in the organization, drags on and on about things which actually are interesting but not relevant for the Daily Scrum, day after day. What are two suggestions you offer the Scrum Master?” Read More »

Answering: “Towards the end of the Sprint Planning meeting, the Product Owner and the Developers have not been able to reach a clear, mutual understanding about the highest order Product Backlog items. Because of this, the Developers could not figure out how many Product Backlog items they could forecast for the upcoming Sprint. The Product Owner did make clear what business objective he is hoping to achieve with this Sprint. Which of the following two actions would you support?”

Towards the end of the Sprint Planning meeting, the Product Owner and the Developers have not been able to reach a clear, mutual understanding about the highest order Product Backlog items. Because of this, the Developers could not figure out how many Product Backlog items they could forecast for the upcoming Sprint. The Product Owner did make clear what business objective he is hoping to achieve with this Sprint. Which of the following two actions would you support?
(choose the best two answers)
A. The Developers forecast the most likely Product Backlog items to meet the business objective and create a Sprint Backlog based on a likely initial design and plan. Once the timebox for the Sprint Planning event is over, they start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint.
B. If all agree they can continue the Sprint Planning meeting as a team past its timebox, until an adequate number of Product Backlog items are well enough understood for the Developers to make a complete forecast. Then start the Sprint.
C. The team splits up and everybody takes as much time as they need to study the Product Backlog items first. The Product Owner should be available to answer individual questions. The group reconvenes when all team members are better prepared and restart the Sprint Planning meeting before the Sprint can start.
D. They discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.

Answering: “Towards the end of the Sprint Planning meeting, the Product Owner and the Developers have not been able to reach a clear, mutual understanding about the highest order Product Backlog items. Because of this, the Developers could not figure out how many Product Backlog items they could forecast for the upcoming Sprint. The Product Owner did make clear what business objective he is hoping to achieve with this Sprint. Which of the following two actions would you support?” Read More »

Answering: “At a Sprint Review meeting, the Product Owner introduces the functionality that is likely to be done over the next Sprints. The Chief Security Officer reminds everyone that through the envisioned functionality, sensitive personal user data will be stored. This might be the subject of external security audits. He reminds everyone of the important non-functional requirements with regards to security. These were not applicable and not considered previously.”

At a Sprint Review meeting, the Product Owner introduces the functionality that is likely to be done over the next Sprints. The Chief Security Officer reminds everyone that through the envisioned functionality, sensitive personal user data will be stored. This might be the subject of external security audits. He reminds everyone of the important non-functional requirements with regards to security. These were not applicable and not considered previously.
What are two good ways the Scrum Team can handle these high-security concerns?
(choose the best two answers)
A. They are discussed, determined, and documented in parallel Sprints to not disturb the actual feature development. Once analyzed, they should be applied to the work already done before further feature development can continue.
B. They should be handled by a separate, specialist team in a parallel Sprint so they can be specifically resolved through an improved application design without hindering functional development.
C. The impact of these security concerns on past AND future work needs to be determined before new Sprints can start. A list of security-related Product Backlog items needs to be passed on to the Product Owner before starting the next Sprint.
D. During the Sprint Retrospective, the Scrum Team assesses how to add these expectations to the Definition of Done so every future Increment will live up to these requirements. If needed they can work with external specialists to better understand the requirements.
E. They are added to the Product Backlog and addressed throughout the next Sprints, combined with creating the business functionality in those Sprints, no matter how small that business functionality.

Answering: “At a Sprint Review meeting, the Product Owner introduces the functionality that is likely to be done over the next Sprints. The Chief Security Officer reminds everyone that through the envisioned functionality, sensitive personal user data will be stored. This might be the subject of external security audits. He reminds everyone of the important non-functional requirements with regards to security. These were not applicable and not considered previously.” Read More »

Answering: “At the seventh Sprint Review, the stakeholders seem disappointed and angry. When asked about it, they say the product being built will not meet their needs and will cost more than they anticipated spending. What factors may have led to this?”

At the seventh Sprint Review, the stakeholders seem disappointed and angry. When asked about it, they say the product being built will not meet their needs and will cost more than they anticipated spending. What factors may have led to this?
(choose the best three answers)
A. The Product Owner has not been interacting frequently with the stakeholders and kept them aware of the progress of the project.
B. The stakeholders haven’t been using the Sprint Reviews to actively engage, and inspect and evaluate progress.
C. Changes to the project plan were not adequately documented and shared. The change request procedure was not diligently followed.
D. The stakeholders were not allowed to enter the development area, or be present at the Daily Scrum.
E. The Scrum Master has not ensured transparency.
F. The Project Management Office (PMO) and its project managers have not been engaged adequately causing the project plan to become inaccurate.

Answering: “At the seventh Sprint Review, the stakeholders seem disappointed and angry. When asked about it, they say the product being built will not meet their needs and will cost more than they anticipated spending. What factors may have led to this?” Read More »

Answering: “In Sprint Planning, the Developers work with the Product Owner to create a forecast for the Sprint. A forecast is a selection of Product Backlog items that the Developers deem feasible to get done by the end of the Sprint. Select two things that explain what “Done” means.”

In Sprint Planning, the Developers work with the Product Owner to create a forecast for the Sprint. A forecast is a selection of Product Backlog items that the Developers deem feasible to get done by the end of the Sprint. Select two things that explain what “Done” means.
(choose the best two answers)
A. All work to create an Increment of software that is ready for acceptance testing by the Product Owner.
B. All work to create an Increment of software that is ready for integration testing.
C. Having an Increment of software that could be released to end users.
D. All work performed as listed in the Definition of Done.
E. All work for which enough expertise and skills are actually present in the Scrum Team.

Answering: “In Sprint Planning, the Developers work with the Product Owner to create a forecast for the Sprint. A forecast is a selection of Product Backlog items that the Developers deem feasible to get done by the end of the Sprint. Select two things that explain what “Done” means.” Read More »