Answering: “The Scrum team has been using the Daily Scrum to report Sprint progress to the Product Owner, because the Product Owner wants to track what every Developer is working on every day. What is the best thing for the Scrum Master to do?”

By Hiro TakashimyaUpdated
Studying for the PSM II exam? Try 10 free practice questions first.Start the free quiz →

The Scrum Master should coach the Product Owner and the Developers on what the Daily Scrum is for, then let them decide how to fix it. Banning the Product Owner or stepping in as a referee treats the symptom and takes ownership away from the team.

Exam Question

The Scrum team has been using the Daily Scrum to report Sprint progress to the Product Owner, because the Product Owner wants to track what every Developer is working on every day. What is the best thing for the Scrum Master to do? (choose the best answer)

  • A. Ask the Product Owner to stop attending the Daily Scrum.
  • B. Coach the Product Owner and Developers on the purpose of Scrum events and let them figure out how to deal with this situation.
  • C. Nothing. The Product Owner can continue to track progress at the Daily Scrum.
  • D. Start attending the Daily Scrum so that whenever the Developers have a conflict with the Product Owner, the Scrum Master can resolve the conflict.

Correct Answer

B. Coach the Product Owner and Developers on the purpose of Scrum events and let them figure out how to deal with this situation.

Why This Is the Correct Answer

The Scrum Guide describes the Daily Scrum as “a 15-minute event for the Developers of the Scrum Team.” Its purpose is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog, not to show a manager who did what. When the event turns into a status report, the Developers stop planning together and start performing for an audience. The Scrum Master is accountable for the team’s effectiveness and for helping everyone understand Scrum. Coaching both sides addresses the real cause, which is a misunderstanding of the event and of self-management. Letting the team choose the fix keeps the solution theirs, so it is more likely to stick.

Why the Other Options Are Wrong

A. Ask the Product Owner to stop attending the Daily Scrum. This removes the person but not the misunderstanding. The Product Owner will likely find another way to demand daily status.

C. Do nothing and let the Product Owner keep tracking progress there. Ignoring a misused event is a failure of the Scrum Master’s accountability. The Daily Scrum is losing its purpose.

D. Attend the Daily Scrum to resolve conflicts between Developers and the Product Owner. This makes the Scrum Master a permanent referee and builds dependency. It also leaves the status-reporting habit untouched.

Exam Tip

In PSM II scenarios where an event is being misused, look for the answer where the Scrum Master teaches the purpose and lets the team own the fix. Answers that ban people or take control are usually wrong.

Key Takeaways

  • The Daily Scrum belongs to the Developers.
  • Daily status reporting to the Product Owner defeats its purpose.
  • The Scrum Master coaches the cause instead of policing the symptom.
Scrum Master PSM II™ Exam Prep

Get ready for the official PSM II exam

90 PSM II practice questions, each with an in-depth explanation like the one above.

  • Practice Mode: study at your own pace and choose the test length.
  • Mock Exam Mode: 30 random questions in 90 minutes, like the real exam.

$29 is ScrumPrep's one-time price. The official PSM II exam fee is paid separately to Scrum.org.

More PSM II exam questions

Practice all 90 PSM II questions →