Answering: “The Scrum Master is a Servant Leader. How does a Scrum Master demonstrate Servant Leadership?”

The Scrum Master is a Servant Leader. How does a Scrum Master demonstrate Servant Leadership?
(choose the best two answers)
A. The Scrum Master facilitates Scrum Events as requested or needed.
B. The Scrum Master coaches the Developers, the Product Owner and the organization how to work empirically.
C. The Scrum Master never intervenes in matters of the Developers, maximizing their autonomy and freedom.
D. The Scrum Master resolves every impediment that the Scrum Team runs into.

Answering: “The Scrum Master is a Servant Leader. How does a Scrum Master demonstrate Servant Leadership?” Read More »

Answering: “You are working with multiple Scrum Teams that are working in the same code base. They suffer from coordination problems and mutual dependencies.”

You are working with multiple Scrum Teams that are working in the same code base. They suffer from coordination problems and mutual dependencies.
True or False: This can be fully addressed with a comprehensive branching and merging model in the version control tool.
A. True
B. False

Answering: “You are working with multiple Scrum Teams that are working in the same code base. They suffer from coordination problems and mutual dependencies.” Read More »

Answering: “Which two statements are the most accurate in regards to scaling Scrum for large projects that require multiple Scrum Teams?”

Which two statements are the most accurate in regards to scaling Scrum for large projects that require multiple Scrum Teams?
(choose the best two answers)
A. A person focusing on the Sprint Backlog of a single Scrum Team is often more productive than that same person working on multiple Scrum Teams at the same time.
B. A well-structured Product Backlog can minimize and often eliminate Developers working on multiple Scrum Teams during a Sprint.
C. A Product Owner must work full time on a single Scrum Team.
D. Customizing the core Scrum framework is necessary to be successful with Scrum at large scale.

Answering: “Which two statements are the most accurate in regards to scaling Scrum for large projects that require multiple Scrum Teams?” Read More »

Answering: “Your Scrum Team has been working together for over a dozen Sprints. The Scrum Team consists of 10 members. Each Sprint takes four weeks. As a Scrum Master, you observe that the Developers are hardly collaborating; during the Sprint, members are working on their own items. You also notice that the items on the Sprint Backlog are mostly unrelated. You suspect that the lack of a Sprint Goal might be the cause.”

Your Scrum Team has been working together for over a dozen Sprints. The Scrum Team consists of 10 members. Each Sprint takes four weeks. As a Scrum Master, you observe that the Developers are hardly collaborating; during the Sprint, members are working on their own items. You also notice that the items on the Sprint Backlog are mostly unrelated. You suspect that the lack of a Sprint Goal might be the cause.
Although you have encouraged the use of a Sprint Goal, both the Product Owner and the Developers have concluded that they are unable to create Sprint Goals based on the wide variety of items on their Product Backlog.
What can explain why this Scrum Team is struggling to craft a Sprint Goal?
(choose all that apply)
A. The Sprints are too long.
B. The Product Owner does not have the mandate to make decisions about items on the Product Backlog nor their ordering.
C. The Product Owner is not communicating the Product Goals that they want to achieve in upcoming Sprints.
D. Scrum might not be the best framework for the work done by this team.
E. The Scrum Team is too big.

Answering: “Your Scrum Team has been working together for over a dozen Sprints. The Scrum Team consists of 10 members. Each Sprint takes four weeks. As a Scrum Master, you observe that the Developers are hardly collaborating; during the Sprint, members are working on their own items. You also notice that the items on the Sprint Backlog are mostly unrelated. You suspect that the lack of a Sprint Goal might be the cause.” Read More »

Answering: “Where should the Daily Scrum be held according to the Scrum Guide?”

Where should the Daily Scrum be held according to the Scrum Guide?
(choose the best answer)
A. Wherever the Developers think is best.
B. In a room where management can listen in.
C. In the coffee corner to confirm this is an informal gathering.
D. Around the Scrum board.
E. In the room that is reserved by the Scrum Master.

Answering: “Where should the Daily Scrum be held according to the Scrum Guide?” Read More »

Answering: “In the Sprint Retrospective, there is discussion that the quality of the Increment is not sufficient for going to production. In response, a Scrum Team member points out the high velocity reached by the team. What are the two best actions for the Scrum Master to take?”

In the Sprint Retrospective, there is discussion that the quality of the Increment is not sufficient for going to production. In response, a Scrum Team member points out the high velocity reached by the team. What are the two best actions for the Scrum Master to take?
(choose the best two answers)
A. Stress the value of working product over measured velocity.
B. Agree and praise the Developers for their hard work, so they are motivated to do even more in the next Sprint.
C. Acknowledge the hard work but remind the Developers that they need to improve in order to do even more in the next Sprint.
D. Facilitate a discussion on how to improve the quality to a level sufficient for production, even if the measured velocity will drop in the next Sprint.

Answering: “In the Sprint Retrospective, there is discussion that the quality of the Increment is not sufficient for going to production. In response, a Scrum Team member points out the high velocity reached by the team. What are the two best actions for the Scrum Master to take?” Read More »