Architecture and infrastructure work is handled inside regular Sprints, emerging alongside working functionality and made visible in the Product Backlog. Scrum has no up-front technical phase before value delivery starts.
Exam Question
After some small experiments with Scrum, your company decides to do a complete project with Scrum. As Scrum Master you have been invited to the “project kick-off meeting” with IT and product management.
The Product Owner asks how many Sprints IT will need to first figure out architecture and infrastructure issues. What are two options to explain how such work is managed using Scrum?
(choose the best two answers)
- A. You explain that product management should not worry about such typical IT work. You inform them that you will assure that the team members reach out to the right people within the IT organization when needed. During each Sprint Planning meeting they will keep the Product Owner updated about the additional effort it will take for that Sprint. That effort will come on top of the effort for the forecasted functional development.
- B. You explain that technical risks are best controlled when architecture and infrastructure emerge alongside the development of functionality. The additional advantage is that business value is created faster and sooner.
- C. You thank product management for understanding that these efforts indeed require effort and budget. You confirm that architecture and infrastructure are best handled before starting Scrum, but that the exact budget is difficult to calculate upfront. You say you will organize this work in timeboxed Sprints of no more than 30 days to limit risk and be transparent toward product management on the actual progress.
- D. You educate the Product Owner to add this work to Product Backlog to uphold transparency. Ask the Developers to plan work during the first several Sprints to estimate these items, while also creating some business functionality in these early Sprints.
Correct Answer
B and D.
Why This Is the Correct Answer
Scrum is founded on empiricism, so risk is reduced by building something real and inspecting it. When architecture grows together with functionality, each Sprint tests technical decisions against working software, which exposes risk early. It also means stakeholders see value from the first Sprint. Option D keeps the work transparent: architecture and infrastructure items go into the Product Backlog, where the Product Owner can order them with full knowledge. The Developers size them and plan them into early Sprints together with business features. Every Sprint should still produce at least one useful Increment, so no Sprint is purely technical.
Why the Other Options Are Wrong
A. Tell product management not to worry about IT work. This hides technical work from the Product Owner and stacks it on top of the forecast. It removes transparency and makes Sprint plans unreliable.
C. Do architecture and infrastructure before starting Scrum. This is a waterfall design phase dressed up as Sprints. It delays value and leaves technical risk untested until functionality is built.
Exam Tip
If a question proposes doing architecture, design or setup “first”, look for the answer where it emerges alongside working functionality and sits in the Product Backlog.
Key Takeaways
- Architecture emerges with functionality in Scrum.
- All work the product needs belongs in the Product Backlog.
- Every Sprint should produce a usable Increment, including the first.

Get ready for the official PSM II exam
90 PSM II practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 30 random questions in 90 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM II exam fee ($250) is paid separately to Scrum.org.
More PSM II exam questions
- Another team’s Scrum Master seeks your advice. The Daily Scrum always runs longer than 15 minutes. The Developers suggest splitting the Scrum Team into two teams. What is your response?
- You are a Scrum Master for a Scrum Team and one of the developers approaches you and says: Every Sprint we are not completing regression testing for all of the selected Product Backlog items in the Sprint. Regression testing is part of the Definition of Done. We have discussed with the Product Owner and decided to change the Definition of Done to remove regression testing.
- A multi-national company is using Scrum for product development of their five major products. What are two good alternatives for how many Product Owners the company should use for these five products?
- Your organization has announced a release to its user base three Sprints from now. To be able to include all functionality in the release, work needs to accelerate. The Product Owner puts some testing from the Definition of Done on hold for the next three Sprints, while adding a generic item to the Product Backlog to resolve this in a future release.
- You are the Scrum Master for three Scrum Teams working on the same product. There is a single Product Backlog that all three Scrum Teams select from. Management is eager to improve the productivity of the teams and wants to standardize velocity across all three teams so that they can see how each team is delivering value. When responding to management, which two statements are appropriate?