Location for the Daily Scrum
The Daily Scrum is a crucial event in the Scrum framework, designed to enhance communication, identify impediments, and promote quick decision-making. This article explores the correct location for holding the Daily Scrum according to the Scrum Guide, providing detailed explanations and insights relevant to the PSM II exam.
Exam Question
Where should the Daily Scrum be held according to the Scrum Guide? (choose the best answer)
- A. Wherever the Developers think is best.
- B. In a room where management can listen in.
- C. In the coffee corner to confirm this is an informal gathering.
- D. Around the Scrum board.
- E. In the room that is reserved by the Scrum Master.
Correct Answer
A. Wherever the Developers think is best.
Explanation
Correct Answer
A. Wherever the Developers think is best: According to the Scrum Guide, the Daily Scrum should be held at a place and time determined by the Developers. The goal is to ensure that the environment is conducive to effective communication and collaboration. This flexibility allows the team to choose a location that best suits their needs and promotes a productive meeting.
Why the Other Answers are Incorrect
B. In a room where management can listen in: The Daily Scrum is primarily for the Developers to synchronize their work and plan for the next 24 hours. Having management listen in can create an atmosphere of surveillance and hinder open communication.
C. In the coffee corner to confirm this is an informal gathering: While the Daily Scrum can be informal, the location should still support focus and effective communication. The coffee corner might be too informal and distracting, detracting from the purpose of the meeting.
D. Around the Scrum board: Although the Scrum board is a useful tool, the Scrum Guide does not mandate that the Daily Scrum must be held around it. The Developers should choose the most effective location, which may or may not involve the Scrum board.
E. In the room that is reserved by the Scrum Master: The Scrum Master facilitates Scrum events as needed but does not dictate the location of the Daily Scrum. The decision should be made by the Developers to ensure it meets their needs.
Responsibilities in Scrum
- Product Owner: The Product Owner does not typically participate in the Daily Scrum but should ensure that the Product Backlog is transparent and well-communicated to support the Developers.
- Scrum Master: The Scrum Master ensures that the Scrum events take place and are productive. They coach the Developers on effective practices but do not decide the location of the Daily Scrum.
- Developers: The Developers are responsible for conducting the Daily Scrum. They decide on the location and format that best supports their collaboration and goal-setting.
Relevance to the PSM II Exam
Understanding the flexibility and purpose of the Daily Scrum is crucial for the PSM II exam. It demonstrates advanced knowledge of Scrum practices and the ability of the Scrum Master to facilitate effective team collaboration. Mastering this concept ensures that Scrum Masters can support their teams in optimizing their communication and productivity.
Key Takeaways
- The Daily Scrum should be held at a place and time determined by the Developers.
- The location should support effective communication and collaboration.
- Flexibility in choosing the location promotes a productive and focused meeting.
Conclusion
The location of the Daily Scrum should be decided by the Developers to ensure it best supports their needs and promotes effective communication. Understanding this principle is crucial for effective Scrum implementation and success in the PSM II exam.

Get ready for the official PSM II exam
90 PSM II practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 30 random questions in 90 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM II exam fee ($250) is paid separately to Scrum.org.
More PSM II exam questions
- In the Sprint Retrospective, there is discussion that the quality of the Increment is not sufficient for going to production. In response, a Scrum Team member points out the high velocity reached by the team. What are the two best actions for the Scrum Master to take?
- True or False: Using Scrum ensures that adding more resources to a product delivery effort proportionally increases the value delivered.” (PSM II)
- After some small experiments with Scrum, your company decides to do a complete project with Scrum. As Scrum Master you have been invited to the “project kick-off meeting” with IT and product management.
- Another team’s Scrum Master seeks your advice. The Daily Scrum always runs longer than 15 minutes. The Developers suggest splitting the Scrum Team into two teams. What is your response?
- You are a Scrum Master for a Scrum Team and one of the developers approaches you and says: Every Sprint we are not completing regression testing for all of the selected Product Backlog items in the Sprint. Regression testing is part of the Definition of Done. We have discussed with the Product Owner and decided to change the Definition of Done to remove regression testing.