In the first Sprint, the Scrum Team should create at least one valuable, useful Increment. The first Sprint is not a phase for documenting requirements, planning the whole project or designing the architecture.
Exam Question
What should the Scrum Team do during the first Sprint?
(choose the best answer)
A. Create at least one valuable and useful Increment.
B. Analyze, describe, and document the requirements for the subsequent Sprints.
C. Make up a plan for the rest of the project.
D. Define the major product features and a release plan architecture.
Correct Answer
A. Create at least one valuable and useful Increment.
Why This Is the Correct Answer
Every Sprint, including the first, follows the same rules. The Scrum Guide says “The entire Scrum Team is accountable for creating a valuable, useful Increment every Sprint.” Building something that works right away gives the team real feedback on the product, the technology and its own way of working. Architecture and infrastructure still get attention, but they emerge alongside working functionality instead of before it. A first Sprint spent only on analysis or planning would produce documents that cannot be inspected the way an Increment can, which delays learning and adds risk.
Why the Other Options Are Wrong
B. Analyze and document requirements for later Sprints. This is a waterfall analysis phase disguised as a Sprint. The Product Backlog is refined continuously, not up front.
C. Make a plan for the rest of the project. Scrum plans empirically, Sprint by Sprint. A detailed long-range plan made before any delivery will be wrong.
D. Define the major features and a release plan architecture. Big up-front design delays value. Architecture should evolve with the Increments.
Exam Tip
Any question about a “first Sprint” or “Sprint 0” has the same answer pattern: the first Sprint delivers a Done, usable Increment just like every other Sprint.
Key Takeaways
- The first Sprint delivers a usable Increment.
- There is no setup or planning Sprint in Scrum.
- Architecture emerges alongside working product.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- True or False: The purpose of a Sprint is to produce a valuable, useful Increment.” (PSPO I)
- Who is accountable for creating a valuable and usable Increment each Sprint?
- How much time is required after a Sprint to prepare for the next Sprint?” (PSPO I)
- True or False: To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, Developers to implement those ideas, and a Scrum Master to help guide the process.” (PSPO I)
- True or False: A Product Owner is essentially the same thing as a traditional Project Manager.