The whole Scrum Team is accountable for creating a valuable, useful Increment each Sprint. The Developers build it, but accountability for the result is shared across the team.
Exam Question
Who is accountable for creating a valuable and usable Increment each Sprint?
(choose the best answer)
A. The Scrum Master.
B. The CEO.
C. The Developers.
D. The Product Owner.
E. The Scrum Team.
Correct Answer
E. The Scrum Team.
Why This Is the Correct Answer
The Scrum Guide states “The entire Scrum Team is accountable for creating a valuable, useful Increment every Sprint.” Each accountability contributes in its own way. The Developers create the usable Increment and instill quality by adhering to the Definition of Done. The Product Owner maximizes the value of what is built by managing the Product Backlog. The Scrum Master makes the team effective. The question uses “valuable and usable”, which includes value, so no single accountability covers it alone. That is why the Scrum Team is the best answer rather than the Developers or the Product Owner.
Why the Other Options Are Wrong
A. The Scrum Master. The Scrum Master is accountable for the team’s effectiveness, not for creating the Increment alone.
B. The CEO. The CEO is not part of the Scrum Team and holds no Scrum accountability for the Increment.
C. The Developers. The Developers create the usable Increment, but value depends on the whole team, including the Product Owner.
D. The Product Owner. The Product Owner is accountable for maximizing value, but not for creating the Increment alone.
Exam Tip
Read the exact words: “valuable and useful Increment” points to the whole Scrum Team, while “usable Increment” or “how to build it” points to the Developers.
Key Takeaways
- The whole Scrum Team owns the Increment’s value and usefulness.
- Each accountability contributes differently.
- Watch small wording differences in accountability questions.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- How much time is required after a Sprint to prepare for the next Sprint?” (PSPO I)
- True or False: To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, Developers to implement those ideas, and a Scrum Master to help guide the process.” (PSPO I)
- True or False: A Product Owner is essentially the same thing as a traditional Project Manager.
- The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?” (PSPO I)
- Which are appropriate topics for discussion in a Sprint Retrospective?” (PSPO I)