An effective Product Owner must give a clear and informed opinion about the Product Backlog. They do not have to satisfy every stakeholder, manage team productivity or act as the only contact for stakeholders.
Exam Question
An effective Product Owner must:
(choose the best answer)
A. ensure that every stakeholder need is met.
B. provide a clear and informed opinion about the Product Backlog.
C. ensure that the team is as productive as possible.
D. be the single point of contact for all stakeholders.
E. All of the above.
F. None of the above.
Correct Answer
B. provide a clear and informed opinion about the Product Backlog.
Why This Is the Correct Answer
The Scrum Guide says “For Product Owners to succeed, the entire organization must respect their decisions.” Those decisions show up in the content and ordering of the Product Backlog. To make them well, the Product Owner needs a clear view of the product’s purpose, customers and market, plus evidence from each Increment. An informed opinion lets the team move quickly and gives stakeholders someone accountable to talk to. Trying to meet every stakeholder need is impossible and would lead to a product with no focus. Productivity of the team is the Developers’ concern, with help from the Scrum Master, and stakeholders may also talk to the Developers directly.
Why the Other Options Are Wrong
A. Ensure every stakeholder need is met. Not every need can or should be met. The Product Owner has to make trade-offs to maximize value.
C. Ensure the team is as productive as possible. Team effectiveness is the Scrum Master’s accountability, and the Developers manage their own work.
D. Be the single point of contact for all stakeholders. Developers often work directly with stakeholders, for example during refinement and the Sprint Review.
E. All of the above. A, C and D are not responsibilities of the Product Owner.
F. None of the above. B is true, so this option fails.
Exam Tip
PSPO II questions often test the Product Owner’s decisiveness. Pick options showing informed decisions and clear opinions over options about pleasing everyone or controlling communication.
Key Takeaways
- The Product Owner makes informed decisions about the Product Backlog.
- Pleasing every stakeholder is not the goal; value is.
- Developers can talk to stakeholders directly.

Get ready for the official PSPO II exam
120 PSPO II practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 40 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO II exam fee ($250) is paid separately to Scrum.org.
More PSPO II exam questions
- Which of the following measures might help you determine whether your product is delivering value to your customer?
- Consider the following three statements:
- You have more ideas for new products than you have money to invest. What should you do?
- Choose the statement that best describes who is responsible for engaging the stakeholders.
- You started measuring product feature usage in your last release. You are surprised to learn that a sizable percentage of the features you thought were very important are never or rarely used.