Answering: “During the Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams identify many dependencies. This makes it hard for them to choose the work they could pull into their individual teams for the next Sprint. No matter how they reorganize the Product Backlog items, they continually find more or new dependencies. What techniques could help this Nexus manage their dependencies effectively?”
[color=#6495ed]Scenario C: Dependencies and Product Backlog Items[/color]
During the Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams identify many dependencies. This makes it hard for them to choose the work they could pull into their individual teams for the next Sprint. No matter how they reorganize the Product Backlog items, they continually find more or new dependencies.
What techniques could help this Nexus manage their dependencies effectively?
(choose the best two answers)
A. The Nexus Integration Team should complete the dependent work ahead of the Sprint for the teams.
B. Reorganize team members between the teams to eliminate cross-team dependencies.
C. Extend the Sprint so that the teams can have more time to compete the dependent work.
D. Reorder Product Backlog items so that you can accommodate dependencies.