A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason

Answering: “A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason:”

A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason:
(choose the best answer)
A. The QA department needs more time to make the previous Increment “Done”.
B. The stakeholders are not happy with the value produced in the previous Sprint.
C. There is no acceptable reason. A new Sprint starts immediately after the conclusion of the previous Sprint.
D. The Product Owner has not identified a Sprint Goal.
E. Not enough Product Backlog items are “Ready”.

Answering: “A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason:” Read More »

As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions

Answering: “As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?” (PSM I)

As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?
(choose the best two answers)
A. The Developers work overtime during this Sprint.
B. Cancel the Sprint.
C. The Developers ensure that the Scrum Team is aware, start the Sprint, and monitor progress.
D. Remove or change selected Product Backlog items.
E. Recruit additional Developers before the work can begin.

Answering: “As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?” (PSM I) Read More »