What happens if the Scrum Team cannot complete its work by the end of the Sprint

Answering: “What happens if the Scrum Team cannot complete its work by the end of the Sprint?” (PSM I)

What happens if the Scrum Team cannot complete its work by the end of the Sprint?
(choose the best answer)
A. The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.
B. The Sprint is extended and future Sprints use this new duration.
C. The Sprint length is unchanged and the Scrum Team continuously learns and adapts.

Answering: “What happens if the Scrum Team cannot complete its work by the end of the Sprint?” (PSM I) Read More »

Which of the following are true about the length of the Sprint

Answering: “Which of the following are true about the length of the Sprint?” (PSM I)

Which of the following are true about the length of the Sprint?
(choose the best answer)
A. All Sprints must be one month or less.
B. The length of the Sprint should be proportional to the work that is done in between Sprints.
C. Sprint length is determined during Sprint Planning, and should be long enough to make sure the Scrum Team can deliver what is to be accomplished in the upcoming Sprint.
D. Sprint length is determined during Sprint Planning, and should hold the time it will take to build the planned features in the upcoming Sprint, but does not include time for any testing.

Answering: “Which of the following are true about the length of the Sprint?” (PSM I) Read More »

What is the key concern when multiple Scrum Teams are working from the same Product Backlog

Answering: “What is the key concern when multiple Scrum Teams are working from the same Product Backlog?” (PSM I)

What is the key concern when multiple Scrum Teams are working from the same Product Backlog?
(choose the best answer)
A. Clear definition of requirements.
B. Making sure there’s enough work for everyone on each team.
C. Meeting original scope projections.
D. Minimizing dependencies between teams.
E. Maximizing velocity.

Answering: “What is the key concern when multiple Scrum Teams are working from the same Product Backlog?” (PSM I) Read More »