Answering: “How much time is required after a Sprint to prepare for the next Sprint?”
How much time is required after a Sprint to prepare for the next Sprint?
(choose the best answer)
A. The break between Sprints is time-boxed to one-week for a one-month Sprint, and usually less for shorter Sprints.
B. None. A new Sprint starts immediately following the end of the previous Sprint.
C. Enough time for the Developers to finish the testing from the last Sprint.
D. Enough time for the requirements for the next Sprint to be determined and documented.
E. All of the above are allowed depending on the situation.
Answering: “How much time is required after a Sprint to prepare for the next Sprint?” Read More »