PSM I exam question
How much time is required after a Sprint to prepare for the next Sprint

Answering: “How much time is required after a Sprint to prepare for the next Sprint?” (PSM I)

By Hiro TakashimyaUpdated
Studying for the PSM I exam? Try 20 free practice questions first.Start the free quiz →

Time Required Between Sprints in Scrum

In Scrum, maintaining a continuous flow of work is crucial for iterative progress and efficiency. Here is an analysis of how much time is required after a Sprint to prepare for the next Sprint:

Exam Question

How much time is required after a Sprint to prepare for the next Sprint? (choose the best answer)

  • A. The break between Sprints is time-boxed to one-week for a one-month Sprint, and usually less for shorter Sprints.
  • B. None. A new Sprint starts immediately following the end of the previous Sprint.
  • C. Enough time for the Developers to finish the testing from the last Sprint.
  • D. Enough time for the requirements for the next Sprint to be determined and documented.
  • E. All of the above are allowed depending on the situation.

Correct Answer

B. None. A new Sprint starts immediately following the end of the previous Sprint.

Explanation

Why B is Correct

In Scrum, there is no break or downtime between Sprints. The next Sprint begins immediately after the conclusion of the previous Sprint. This approach ensures continuous progress and a steady flow of work. Activities such as testing, refinement, and documentation are integrated within the Sprint itself, rather than being left for a period between Sprints.

Key Points

  • Continuous Flow: The next Sprint starts immediately to maintain momentum and ensure continuous delivery of value.
  • Integrated Activities: Testing, refinement, and documentation should be planned and executed within the Sprint, not left for after its conclusion.
  • Scrum Principles: Adhering to Scrum principles ensures that all necessary preparation happens as part of the Sprint events, maintaining a consistent and predictable cadence.

Roles and Responsibilities in Scrum

  • Product Owner: Ensures that the Product Backlog is refined and ordered, and that there are sufficient ready items for the next Sprint.
  • Scrum Master: Facilitates the Scrum process and ensures that the team adheres to Scrum principles, including the seamless transition between Sprints.
  • Developers: Complete all work, including testing and documentation, within the Sprint, ensuring they are prepared to start the next Sprint immediately.

Relevance to the PSM I Exam

Understanding the seamless transition between Sprints and the integration of all necessary activities within the Sprint is crucial for the PSM I exam. This knowledge helps candidates appreciate the importance of maintaining a continuous workflow in Scrum.

Conclusion

No time is required after a Sprint to prepare for the next Sprint. A new Sprint starts immediately following the end of the previous Sprint, ensuring continuous progress and adherence to Scrum principles.

Scrum Master PSM I™ Exam Prep

Get ready for the official PSM I exam

480 PSM I practice questions, each with an in-depth explanation like the one above.

  • Practice Mode: study at your own pace and choose the test length.
  • Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.

$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.

More PSM I exam questions

Practice all 480 PSM I questions →

You cannot copy content of this page