Time Required Between Sprints in Scrum
In Scrum, maintaining a continuous flow of work is crucial for iterative progress and efficiency. Here is an analysis of how much time is required after a Sprint to prepare for the next Sprint:
Exam Question
How much time is required after a Sprint to prepare for the next Sprint? (choose the best answer)
- A. The break between Sprints is time-boxed to one-week for a one-month Sprint, and usually less for shorter Sprints.
- B. None. A new Sprint starts immediately following the end of the previous Sprint.
- C. Enough time for the Developers to finish the testing from the last Sprint.
- D. Enough time for the requirements for the next Sprint to be determined and documented.
- E. All of the above are allowed depending on the situation.
Correct Answer
B. None. A new Sprint starts immediately following the end of the previous Sprint.
Explanation
Why B is Correct
In Scrum, there is no break or downtime between Sprints. The next Sprint begins immediately after the conclusion of the previous Sprint. This approach ensures continuous progress and a steady flow of work. Activities such as testing, refinement, and documentation are integrated within the Sprint itself, rather than being left for a period between Sprints.
Key Points
- Continuous Flow: The next Sprint starts immediately to maintain momentum and ensure continuous delivery of value.
- Integrated Activities: Testing, refinement, and documentation should be planned and executed within the Sprint, not left for after its conclusion.
- Scrum Principles: Adhering to Scrum principles ensures that all necessary preparation happens as part of the Sprint events, maintaining a consistent and predictable cadence.
Roles and Responsibilities in Scrum
- Product Owner: Ensures that the Product Backlog is refined and ordered, and that there are sufficient ready items for the next Sprint.
- Scrum Master: Facilitates the Scrum process and ensures that the team adheres to Scrum principles, including the seamless transition between Sprints.
- Developers: Complete all work, including testing and documentation, within the Sprint, ensuring they are prepared to start the next Sprint immediately.
Relevance to the PSM I Exam
Understanding the seamless transition between Sprints and the integration of all necessary activities within the Sprint is crucial for the PSM I exam. This knowledge helps candidates appreciate the importance of maintaining a continuous workflow in Scrum.
Conclusion
No time is required after a Sprint to prepare for the next Sprint. A new Sprint starts immediately following the end of the previous Sprint, ensuring continuous progress and adherence to Scrum principles.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- What is the accountability of the Product Owner during Sprint 0?” (PSM I)
- True or False: A properly functioning Scrum Team will have at least one Release Sprint.
- Which three of the following are timeboxed events in Scrum?” (PSM I)
- What happens if the Scrum Team cannot complete its work by the end of the Sprint?” (PSM I)
- Which of the following are true about the length of the Sprint?” (PSM I)