The Concept of a Release Sprint in Scrum
In Scrum, the framework emphasizes continuous delivery of potentially releasable increments. Let’s examine the concept of a Release Sprint and whether it is a necessary component of a properly functioning Scrum Team.
Exam Question
True or False: A properly functioning Scrum Team will have at least one Release Sprint.
- A. True
- B. False
Correct Answer
B. False
Explanation
Why B is Correct
B. False:
In Scrum, there is no concept of a “Release Sprint.” Each Sprint is expected to produce a potentially releasable Increment of the product. This means that the Scrum Team aims to deliver usable and valuable increments at the end of each Sprint, not just at the end of a “Release Sprint.” The focus is on continuous delivery rather than waiting for a special Sprint to release the product.
Key Points
- Continuous Delivery: Each Sprint should result in a potentially releasable product increment.
- No Special Sprints: Scrum does not prescribe any special Sprints (like a Release Sprint) for releasing the product.
- Iterative Progress: The iterative nature of Scrum ensures that value is delivered continuously and incrementally.
Roles and Responsibilities in Scrum
- Product Owner: Orders the Product Backlog to ensure that the most valuable and necessary items are worked on in each Sprint.
- Scrum Master: Facilitates the Scrum process and ensures that the team adheres to Scrum principles, including delivering potentially releasable increments each Sprint.
- Developers: Work collaboratively to deliver a potentially releasable increment at the end of each Sprint, ensuring continuous delivery of value.
Relevance to the PSM I Exam
Understanding that there is no concept of a “Release Sprint” in Scrum is crucial for the PSM I exam. This knowledge helps candidates appreciate the importance of continuous delivery and the iterative nature of Scrum, where each Sprint results in a potentially releasable increment.
Conclusion
A properly functioning Scrum Team does not have a “Release Sprint.” Instead, each Sprint should deliver a potentially releasable increment, ensuring continuous delivery of value and adherence to Scrum principles.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- Which three of the following are timeboxed events in Scrum?” (PSM I)
- What happens if the Scrum Team cannot complete its work by the end of the Sprint?” (PSM I)
- Which of the following are true about the length of the Sprint?” (PSM I)
- Who can abnormally terminate a Sprint?
- What are two good answers a Scrum Master might give their manager and Product Owner when they say they have allocated budget for a first Sprint to figure out architecture and infrastructure issues?