Answering: “As a Product Owner you become aware that the quality assurance criteria, defined in the Definition of Done, were not met for the latest Increment. Which of the following statements are true?”
As a Product Owner you become aware that the quality assurance criteria, defined in the Definition of Done, were not met for the latest Increment. Which of the following statements are true?
(choose the best four answers)
A. The Scrum Team should not release the Increment.
B. The project manager cannot effectively update the plan.
C. The next Sprint may be interrupted when quality issues are encountered.
D. The indication of progress on the Product Backlog is not transparent.
E. The incomplete Sprint Backlog items should be returned to the Product Backlog.