Answering: “During a Sprint, it has been determined that the Developers will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected?”
During a Sprint, it has been determined that the Developers will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected?
(choose the best answer)
A. The Product Owner and all stakeholders.
B. The Product Owner and the Developers.
C. The Developers.
D. The Scrum Master, the project manager and the Developers.