False. Scrum does not require multiple Scrum Teams to start their Sprints on the same day. Teams may choose to align their Sprints, but that is a choice, not a rule.
Exam Question
True or False: Multiple Scrum Teams working on the same project must have the same Sprint start date.
- A. True
- B. False
Correct Answer
B. False
Why This Is the Correct Answer
The Scrum Guide sets rules for one Scrum Team. It says Sprints are fixed-length events of one month or less, and that a new Sprint starts immediately after the previous one ends. It says nothing about synchronizing start dates across teams. When several teams work on the same product, they share one Product Backlog, one Product Owner and one Definition of Done, and they must produce an integrated Increment. Aligned Sprints can make that integration easier, and scaling frameworks like Nexus use a shared Sprint cadence. Even so, aligned dates are a useful practice, not something Scrum itself demands.
Why the Other Options Are Wrong
A. True This turns a helpful scaling practice into a Scrum rule. The Guide does not require a common start date.
Exam Tip
When a True/False statement adds a “must” that is not in the Scrum Guide, ask yourself where the rule would come from. If you cannot point to it, the answer is usually False.
Key Takeaways
- Scrum does not require teams to share a Sprint start date.
- Shared Sprint cadence can help integration but is optional.
- Teams on one product still produce one integrated Increment.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- Which three of the following are feedback loops in Scrum?” (PSM I)
- When can Developers cancel a Sprint?” (PSM I)
- A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason:
- Which of the following is required by Scrum?” (PSM I)
- How much time is required after a Sprint to prepare for the next Sprint?” (PSM I)